Daye peak cement warehouse system transformation to see results
Release time:
2023-03-21
daye peak original P.O42.5 bagged and bulk cement can only be dumped through 1# dump hoist. as the sales proportion of P.O42.5 cement is about 80%, 1# dump hoist is in a high-load operation state for a long time and the supply capacity is obviously insufficient, which not only affects the cement distribution efficiency but also has high equipment operation risk. 2# dump hoist can only distribute P.C42.5 and M32.5 cement, due to the small number of shipments, the average daily downtime is about 8 hours, and the ash pouring capacity is limited, and the efficiency cannot be effectively exerted.
This technical renovation has changed the situation that the original 2# dump hoist cannot distribute P.O42.5 cement by diverting the outbound P.O42.5 cement to the 2# dump hoist, reducing the idle time of the hoist and improving the utilization rate of the 2# dump hoist. At the same time, in combination with the product structure of the enterprise, the 1# bulk warehouse will be changed from distributing P.C42.5 bagged cement to PO42.5 bags and bulk cement, by improving the utilization rate of the reverse hoist and the bulk cement warehouse, the purpose of improving the cement delivery capacity is achieved while reducing the risk of high-load operation of the equipment. After the transformation of
, the daily maximum shipment volume of Daye peak increased by nearly 2000 tons compared with that before the transformation, the delivery capacity was greatly improved, the delivery speed was significantly improved, and the transformation effect was unanimously affirmed by the employees of the enterprise and the drivers of cement trucks. (Huang Bide, Chen Cuihong)
More information
Tianjin Flemish Company Donates Anti-epidemic Materials
On the morning of July 13, Tianjin Jianfeng Flanders Pharmaceutical Technology Development Co., Ltd. donated materials to the Tianjin Development Zone Charity Association to help the development zone community fight the epidemic.
2020
08-05
In late July, leaders of the group company Jiang Xiaomeng, Yu Jianhong, Chen Tianci and Qin Xuping visited subordinate enterprises separately and sent heatstroke prevention and cooling supplies to employees working under high temperature, urging everyone to pay attention to heatstroke prevention and cooling and safe production work to ensure good physical condition.
2020
08-05
On July 17 and 18, the Group's work analysis meeting for the first half of 2020 was held at the Peak Building of the Group's headquarters to summarize and review the work in the first half of the year and make arrangements for the work in the second half of the year.
2020
08-05
The company requires to do a good job in summer safety production
The high temperature season is approaching, and the group company issued a notice a few days ago to make arrangements for safe production in summer.
2020
08-05
The company requires to do a good job in summer safety production
The high temperature season is approaching, and the group company issued a notice a few days ago to make arrangements for safe production in summer. The notice requires all subordinate units of the company to attach great importance to the work of production safety in summer, and all production and business units should hold a special meeting on production safety in summer. According to the characteristics of production in summer, they should focus on safety risk analysis for mines, outdoor operations and high-temperature posts, and implement control measures to avoid the occurrence of safety accidents such as scalding, heatstroke and electric shock. In order to further strengthen the safety production management in the high temperature season, the notice requires the main person in charge of each production and business unit to lead a team to conduct a comprehensive inspection of the production and business premises according to the characteristics of summer production; strengthen the daily safety production inspection of key posts and special posts; timely rectify the found unsafe behaviors and hidden dangers; Strengthen the management of the storage and use of flammable, explosive, dangerous chemicals and drugs; cooling measures shall be taken for the space exceeding the storage temperature limit of articles. If it is found that the electrical equipment circuit and exhaust fan circuit are aged and damaged, replace them in time and keep the grounding wire in good condition. Do a good job in checking the fire pool, pipeline water pressure and fire extinguishing equipment to ensure that the fire fighting facilities are sensitive, intact and reliable. The high temperature in summer is also a period of frequent occurrence of heatstroke and other diseases. The notice requires all units to do a good job in heatstroke prevention and cooling, implement various relevant measures, and equip necessary cooling facilities or materials such as fans, air conditioners, ice cubes and other cooling facilities or materials according to the conditions of the production site; do a good job in the distribution of heatstroke prevention drugs, supplies and cool drinks in workshops, warehouses, construction sites and other production lines; strengthen canteen management to prevent food poisoning. (this newspaper reporter)
2020
07-22
The company requires to do a good job in summer safety production
The high temperature season is approaching, and the group company issued a notice a few days ago to make arrangements for safe production in summer. The notice requires all subordinate units of the company to attach great importance to the work of production safety in summer, and all production and business units should hold a special meeting on production safety in summer. According to the characteristics of production in summer, they should focus on safety risk analysis for mines, outdoor operations and high-temperature posts, and implement control measures to avoid the occurrence of safety accidents such as scalding, heatstroke and electric shock. In order to further strengthen the safety production management in the high temperature season, the notice requires the main person in charge of each production and business unit to lead a team to conduct a comprehensive inspection of the production and business premises according to the characteristics of summer production; strengthen the daily safety production inspection of key posts and special posts; timely rectify the found unsafe behaviors and hidden dangers; Strengthen the management of the storage and use of flammable, explosive, dangerous chemicals and drugs; cooling measures shall be taken for the space exceeding the storage temperature limit of articles. If it is found that the electrical equipment circuit and exhaust fan circuit are aged and damaged, replace them in time and keep the grounding wire in good condition. Do a good job in checking the fire pool, pipeline water pressure and fire extinguishing equipment to ensure that the fire fighting facilities are sensitive, intact and reliable. The high temperature in summer is also a period of frequent occurrence of heatstroke and other diseases. The notice requires all units to do a good job in heatstroke prevention and cooling, implement various relevant measures, and equip necessary cooling facilities or materials such as fans, air conditioners, ice cubes and other cooling facilities or materials according to the conditions of the production site; do a good job in the distribution of heatstroke prevention drugs, supplies and cool drinks in workshops, warehouses, construction sites and other production lines; strengthen canteen management to prevent food poisoning. (this newspaper reporter)
2020
07-31