Ignition! Three cement enterprises to complete the annual overhaul has resumed production
Release time:
2022-03-11
According to the peak shift production requirements of Yunnan province's industry and information technology, environmental protection and other departments and the arrangement of industry associations, cement enterprises in southwest Yunnan stopped production for
50days in the first quarter. Yunnan peak started its annual overhaul from 2# September 5 , with emphasis on the replacement of 16 m kiln cylinder and the replacement of refractory materials such as decomposition furnace and rotary kiln, the cleaning of the raw material warehouse and the replacement of the breather cloth of the inflatable box involve a wide range, many cross operations and tight construction time. After careful organization and the full cooperation of the participating teams, while successfully completing the established maintenance projects, the phenomenon of running and dripping was comprehensively controlled and rectified. On the afternoon of 3 May 4 , Yunnan Peak successfully completed its annual overhaul and resumed production after ignition. Daye Peak 1
February22 began to overhaul the 2 cement mill. In the following more than a month, the cement mill, kiln system, grate cooler, coal mill, raw mill, packaging hoist and other equipment were successively overhauled and renovated. In order to ensure the quality of maintenance and technical transformation, during this period, Daye Peak strictly implemented the new safety production law, through the advance of the outsourcing team safety disclosure, do a good job in epidemic prevention and control, the implementation of the outsourcing unit operation risk assessment, operation ticket management, safety guardian system, to ensure the safety during maintenance. At the same time, in order to give full play to the work initiative of grass-roots employees, excellent mechanics and post workers are selected to participate in the whole process of overhaul, such as overhaul plan formulation, operation risk assessment, machine material consumption approval, control of key quality nodes, equipment test machine acceptance, etc. The initiative and enthusiasm of employees are significantly improved, and the level of work skills is also improved. 3 August 8 , Daye Peak Rotary Kiln was successfully ignited. This overhaul is the first comprehensive overhaul since Guizhou Huangping Peak was put into production. In order to carry out the maintenance work smoothly, Huang Ping Jianfeng made a thorough maintenance plan in advance, repeatedly reviewing and deliberating the qualification of the construction team entering the factory, the construction plan and schedule, and the procurement of relevant equipment and parts, and the rectification of each system was clearly implemented to the responsible person. In order to enable front-line employees to increase their knowledge and improve their skills from the overhaul, Huang Ping Jianfeng carried out the training on the overhaul site, invited the technicians of relevant manufacturers to provide technical guidance, and arranged the employees of large-scale inspection and other posts to help the outsourcing units and follow the shift to learn, so that the employees learned more knowledge and experience during the overhaul process. On the morning of 3
May9 , Huang Ping Jianfeng finished his first major repair and successfully ignited and resumed production. (Song Xiaofei Wang Yuhua
Huang Xuguang / Wen Liu Feng /)
More information
Editor's note: During the National Day, the "Jinhua New Observation" column of Jinhua TV Station launched a series of reports on "National Day New Observation: New Development of Old Enterprises" to understand the new developments of those old enterprises that have grown up with New China in the new era. October 3 broadcast of the "peak of the 'centennial 'ideal", about the development of the peak group and the future direction of development. The "century" ideal of the peak Jinhua TV reporter Wang Dujuan Jiang Qian host: speaking of Zhejiang Jianfeng Group Co., Ltd., Jinhua people are no stranger. The older generation of Jinhua people are more familiar with, may be the predecessor of Jianfeng Group-Jinhua Cement Factory. Open the first old photo 58 years ago, surrounded by mountains and a rice field in the middle. Old Jinhua can see at a glance that this is the Wise Temple, 8 kilometers north of Jinhua City and east of the former Zhuangtou of Luodian Town. In August 1958, the first group of pioneers came here and built Jinhua's first cement factory on a desolate hillside of 16.94 mu with a pair of hands and warm blood. From the earliest cattle-drawn ball forming machine to the electric ball forming machine, from pure manual labor to machine substitution, it took 26 years of hard work. By 1983, the annual output of peak cement reached 120000 tons, the output value was 6.75 million yuan, and the profit was 2.4 million yuan. In these 26 years, the cement plant has experienced a difficult period of the country, and the ten-year catastrophe of the "Cultural Revolution" has finally ushered in a good time of reform and opening up with tenacious vitality, laying the foundation for steady development in the future. Looking at these old pictures,
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Jianfeng won the Zhejiang Industrial Award
A few days ago, we learned from the relevant departments of Zhejiang Province that the company won the 2016 "Zhejiang Industrial Award Silver Award". Zhejiang Industrial Award was established in 2014 and is selected every two years. The purpose of carrying out the selection and commendation of the Zhejiang Industrial Awards is to thoroughly implement the "August 8 Strategy", comprehensively implement the innovation-driven development strategy, speed up the industrial transformation and upgrading with the "four for three" as the starting point, and commend the adherence to the scientific concept of development. adhere to industry, conscientiously fulfill social responsibilities, establish a modern enterprise system, and take a new road of industrialization with characteristics. The evaluation work is jointly organized and implemented by Zhejiang Industrial Economic Federation, Enterprise Federation, Entrepreneur Association, relevant provincial industry associations, municipal industrial economic federations, enterprise federations, entrepreneur associations, and relevant units. The award review committee is composed of relevant government departments, provincial "three committees", relevant provincial industry associations, and experts in industrial economy, management, finance, taxation, quality, environmental protection, safety, technology, and law, the participating enterprises are comprehensively evaluated from the aspects of industry demonstration role, scientific and technological innovation, economic benefits, resource utilization, environmental protection, brand strategy, product quality, production safety, social responsibility, enterprise management, human resources and so on. "The enterprises that have won the Zhejiang Industrial Award this time are all outstanding enterprises that have made significant contributions to the promotion of Zhejiang's economic development; they are all leading enterprises, backbone enterprises, and high-growth enterprises from different industries, representing the scale of Zhejiang's industrial development. The direction and leading spirit represent the highest level of Zhejiang's industrial development." According to the organizers related negative
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-30
Peak two enterprises were commended
On September 23, the launching ceremony of the 2016 Jinhua Zhejiang Shopping Festival and the 2015 Jinhua Honest Enterprise Commendation Conference were held in the urban people's square. Jianfeng Group's Jinhua Jianfeng Pharmacy Chain Co., Ltd. and Zhejiang Jianfeng International Trade Co., Ltd. were commended.
2020
07-31