Technical renovation of hydraulic system of Yunnan Jianfeng 1# roller press completed
Release time:
2021-02-10
Yunnan Jianfeng 1# Roller Press Hydraulic System Technical Renovation Completed
On January 30, Yunnan Jianfeng Cement Company completed the acceptance of the technical renovation of the 1# Roller Press Hydraulic System and put it into operation. This is also the first technical renovation project completed by Yunnan Jianfeng in 2021.
At present, the operation capacity of Yunnan Peak Mill is larger than the design capacity, the operation condition is unstable, and the phenomenon of jump stop and large roller will occur, which will have a great impact on the reducer and affect the normal operation and civilized hygiene. In this hydraulic system control reform, on the basis of the original hydraulic cylinder, a hydraulic oil station is added and the control system is reformed. The two modes of constant pressure operation and constant roller gap operation can be switched, which can avoid jumping and stopping caused by unstable working conditions and roller deviation. Through the actual operation observation, the stability of the operating conditions after the transformation is better than the original, and the improvement treatment and effect have yet to be explored and verified. (Lou Xuxin)
On January 30, Yunnan Jianfeng Cement Company completed the acceptance of the technical renovation of the hydraulic system of the 1# roller press and put it into operation. This is also the first technical renovation project completed by Yunnan Jianfeng in 2021.
At present, the operation capacity of Yunnan Peak Mill is larger than the design capacity, the operation condition is unstable, and the phenomenon of jump stop and large roller will occur, which will have a great impact on the reducer and affect the normal operation and civilized hygiene. In this hydraulic system control reform, on the basis of the original hydraulic cylinder, a hydraulic oil station is added and the control system is reformed. The two modes of constant pressure operation and constant roller gap operation can be switched, which can avoid jumping and stopping caused by unstable working conditions and roller deviation. Through the actual operation observation, the stability of the operating conditions after the transformation is better than the original, and the improvement treatment and effect have yet to be explored and verified. (Lou Xuxin)
More information
Peak re-listed China's top 100 cement production capacity Daye peak won the "smart factory leader"
On July 11-12, the 2022 China Cement Industry Summit and TOP100 Award Ceremony organized by China Cement Network, an authoritative media of China's cement industry, was held in Hangzhou. Jianfeng Group once again ranked among the top 100 cement clinker production capacity in China.
2022
08-04
On the afternoon of July 12, the party Committee of the group company held a special meeting attended by party Committee members, senior and middle-level management backbones, heads of grass-roots party organizations and all party members of the group headquarters to learn and convey the spirit of the 15th party congress of the communist party of China in Zhejiang province.
2022
07-24
On the morning of July 1, more than 40 members of the group's party committee, party members of various branches of the group headquarters, and party members of subordinate enterprise branches went to the Shuanglong Hydropower Station, the Red Education Base of Jinhua City, to receive party spirit and revolutionary tradition education.
2022
07-14
Vocational skill level identification examination!
On June 16 and 18, the theoretical and practical examinations for the determination of professional skill level in the peak pharmaceutical sector were held successively in Jinxi pharmaceutical factory. The independent identification of vocational skill level includes three occupations (types of work): pharmaceutical preparation worker, chemical inspector and organic synthesis worker, basically covering the main posts in the pharmaceutical sector, with a total of 125 employees signing up for the identification.
2022
06-21
On June 16, the Jianfeng Pharmaceutical Quality Research and Development Party Branch and the Jinhua Vocational Skills Management Service Center Party Branch held a signing ceremony in Jinxi Factory to establish a party building alliance.
2022
06-21
Jinhua Mayor Xing Zhihong to Peak Research
On the afternoon of June 1, Jinhua Mayor Xing Zhihong, Wucheng District Party Committee Secretary Gao Feng, District Mayor Hu Yuxian, and heads of the Municipal Economic and Information Bureau, Development and Reform Bureau and other departments went to the group headquarters to discuss and exchange with the leaders of the group company to understand the development of the enterprise. Solicit opinions and suggestions from enterprises on government work. After understanding the current business situation of the peak, Xing Zhihong pointed out that focus, follow the right path, frontier, steady, is the peak to long-term prosperity of the magic weapon, must continue to adhere.
2022
06-13