Transformation of Daye Peak Total Drop System
Release time:
2020-07-22
Daye Peak Total Descent System Renovation
News from our newspaper 4# July 1 - 10 , Daye Peak Cement Company used the gap before putting into production after overhaul to renovate the total descent system.
The background operating system of Daye Peak General Step-down Station has poor channel and delayed operation due to the aging of communication equipment. The main transformer's up-down gear is not timely, and the capacitor closing and opening do not respond. The instructions for 10kV switch cabinet such as opening and closing are not executed or delayed, and the basic readings in the background, such as duty log and measurement data, are sometimes absent, it seriously affects the safe, stable and orderly operation of power distribution equipment, and also brings great troubles to the personnel on duty. Moreover, according to the service life of the equipment, Daye Peak has been in operation for 11 years and must be upgraded and replaced.
years later due to the impact of the epidemic, equipment procurement and processing of accessories due to logistics restrictions can not be in place in time, after the winning manufacturer and coordination with all parties, with the epidemic relief, finally in 3 29 from Wuhan to the plant. Daye Peak immediately contacted the power supply ground dispatching station and delayed the power outage to 4 July 1 - 2 . Considering the importance of internal communication, the internal communication network was first reformed, the original communication management machine, GPS timing system and 8 relay protection devices were replaced, the background power monitoring and management software was upgraded, the setting value of 10KV relay protection was recalculated and input, and 11 electric meters were newly installed (for data collection of energy management system), after repeated debugging and trial operation, the overall feeling is that the communication channel is unblocked and there is no "blocking" phenomenon. The response to the switch-on and switch-off instructions of the main transformer and the 10KV switch cabinet is timely. After the background upgrade, the desktop data is stable, the report data is true and reliable, and the equipment runs safely and orderly.
After hard work, the renovation was successfully debugged before the kiln was ignited and produced, without affecting the production, delivery and overhaul of finished products. The quality of the renovation project has achieved the expected results. At the same time, Daye Peak will also refer to the later planning plan of Huangshi power transmission network and the requirements of dispatching data collection, replace the original communication management machine according to the specific conditions of the upper substation (axle transformer), and use optical transmission equipment to transmit the information of total reduction, waste heat and safety network to the dispatching. It is planned to overhaul and implement it next year.
After transformation and upgrading, the system communication speed is improved, the data collection time is improved, the information (telemetry, remote signaling, remote control) response efficiency is improved, and the safety and reliability of the communication system are guaranteed. (Zhang Qingyu)
More information
Editor's note: During the National Day, the "Jinhua New Observation" column of Jinhua TV Station launched a series of reports on "National Day New Observation: New Development of Old Enterprises" to understand the new developments of those old enterprises that have grown up with New China in the new era. October 3 broadcast of the "peak of the 'centennial 'ideal", about the development of the peak group and the future direction of development. The "century" ideal of the peak Jinhua TV reporter Wang Dujuan Jiang Qian host: speaking of Zhejiang Jianfeng Group Co., Ltd., Jinhua people are no stranger. The older generation of Jinhua people are more familiar with, may be the predecessor of Jianfeng Group-Jinhua Cement Factory. Open the first old photo 58 years ago, surrounded by mountains and a rice field in the middle. Old Jinhua can see at a glance that this is the Wise Temple, 8 kilometers north of Jinhua City and east of the former Zhuangtou of Luodian Town. In August 1958, the first group of pioneers came here and built Jinhua's first cement factory on a desolate hillside of 16.94 mu with a pair of hands and warm blood. From the earliest cattle-drawn ball forming machine to the electric ball forming machine, from pure manual labor to machine substitution, it took 26 years of hard work. By 1983, the annual output of peak cement reached 120000 tons, the output value was 6.75 million yuan, and the profit was 2.4 million yuan. In these 26 years, the cement plant has experienced a difficult period of the country, and the ten-year catastrophe of the "Cultural Revolution" has finally ushered in a good time of reform and opening up with tenacious vitality, laying the foundation for steady development in the future. Looking at these old pictures,
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Jianfeng won the Zhejiang Industrial Award
A few days ago, we learned from the relevant departments of Zhejiang Province that the company won the 2016 "Zhejiang Industrial Award Silver Award". Zhejiang Industrial Award was established in 2014 and is selected every two years. The purpose of carrying out the selection and commendation of the Zhejiang Industrial Awards is to thoroughly implement the "August 8 Strategy", comprehensively implement the innovation-driven development strategy, speed up the industrial transformation and upgrading with the "four for three" as the starting point, and commend the adherence to the scientific concept of development. adhere to industry, conscientiously fulfill social responsibilities, establish a modern enterprise system, and take a new road of industrialization with characteristics. The evaluation work is jointly organized and implemented by Zhejiang Industrial Economic Federation, Enterprise Federation, Entrepreneur Association, relevant provincial industry associations, municipal industrial economic federations, enterprise federations, entrepreneur associations, and relevant units. The award review committee is composed of relevant government departments, provincial "three committees", relevant provincial industry associations, and experts in industrial economy, management, finance, taxation, quality, environmental protection, safety, technology, and law, the participating enterprises are comprehensively evaluated from the aspects of industry demonstration role, scientific and technological innovation, economic benefits, resource utilization, environmental protection, brand strategy, product quality, production safety, social responsibility, enterprise management, human resources and so on. "The enterprises that have won the Zhejiang Industrial Award this time are all outstanding enterprises that have made significant contributions to the promotion of Zhejiang's economic development; they are all leading enterprises, backbone enterprises, and high-growth enterprises from different industries, representing the scale of Zhejiang's industrial development. The direction and leading spirit represent the highest level of Zhejiang's industrial development." According to the organizers related negative
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-30
Peak two enterprises were commended
On September 23, the launching ceremony of the 2016 Jinhua Zhejiang Shopping Festival and the 2015 Jinhua Honest Enterprise Commendation Conference were held in the urban people's square. Jianfeng Group's Jinhua Jianfeng Pharmacy Chain Co., Ltd. and Zhejiang Jianfeng International Trade Co., Ltd. were commended.
2020
07-31