April 10 Ignition Feeding Daye Peak Restart Successfully
Release time:
2020-07-22
4# February 10 Ignition Feeding
Daye Peak Successfully Restarted
News 4 10 14 58 Points, Daye Peak Cement Company Overcame the Difficulties Caused by the New Crown Epidemic, after more than 60 days of closed overhaul and renovation, the ignition and feeding were finally successful, and the official "restart " .
According to the plan before the Spring Festival, this overhaul includes technical renovation of grate cooler, replacement of rotary kiln cylinder, technical renovation of cement mill, renovation of mixed material feeding system, kiln process overhaul, etc. Due to the outbreak of new coronary pneumonia before the Spring Festival, Daye Peak is on the edge of Wuhan, the core area of the epidemic, prevention and control pressure is very great. Since the Spring Festival holiday on 1 23 , Daye Peak has started the prevention and control of the new coronary pneumonia epidemic according to the standards of the period of "SARS " in accordance with the requirements of the Group. With the change of the epidemic situation, daye peak adjusted its work plan in time according to the needs of production and operation and the prediction of the market. the original plan was to stop production and overhaul on 1 27 and postpone it to 2 . it was not until the raw materials in stock were consumed and the clinker was fully stored in the warehouse that the whole line was shut down, and maintenance was started while epidemic prevention.
According to the particularity of the long construction period, strong professionalism and many outsourcing units of this overhaul and technical renovation, Daye Peak actively coordinated with relevant departments of Daye and Baoan Town, mobilized the heads of various departments and professional personnel of the manufacturing department, and selected the civil construction team to be stationed in the factory. For projects with long overhaul time and many overlapping tasks, Daye Peak first organized personnel to conduct closed overhaul, the left-behind management personnel, mechanics and electricians dismantled the grate cooler frame by themselves, reformed the cement grinding machine, and organized the civil construction of mixed materials. After the frame of
grate cooler was removed, Daye Peak began to contact the maintenance team to enter the factory. At that time, although some progress was made in the prevention and control of the epidemic, the previously identified maintenance teams still played "retreat " . After multi-party coordination and active docking with other maintenance units, with the active cooperation of relevant departments in daye city, the first maintenance team successfully entered the factory on 2 20 . With the follow-up of various work, the number of outsourcing personnel reached 248 at the peak of maintenance work. The technical renovation project was implemented in an orderly manner as planned. The technical renovation of
grate cooler is the most important item in the technical renovation plan of Daye Peak 2020 . Due to the impact of the epidemic, the personnel of the design institute originally responsible for this work were unable to be in place for a long time. Daye Peak actively coordinated, purchased relevant materials in advance, contacted the units that had business cooperation with the company, coordinated and organized personnel to be added to the construction team, and contacted the local construction team for preliminary civil work when the design institute was unable to arrange civil work, effectively reducing the impact of the epidemic on the maintenance period.
In order to ensure the smooth progress of the maintenance work while doing a good job in epidemic prevention and control, Daye Peak departments actively cooperate, canteens do a good job in food protection, procurement departments do a good job in maintenance materials and epidemic prevention materials protection, manufacturing department arranges work in the management group, and departments arrange factory workers to use their free time to assist in cleaning up the site and carrying materials, and cooperate with the work within their capabilities. In this process, the person in charge of the relevant departments of technological transformation used the maintenance meeting every day to communicate and coordinate in advance to ensure the smooth progress of the overall construction.
During the overhaul, Daye Peak revised the five stages of the epidemic prevention and control plan according to the changes in the epidemic situation and the need for overhaul, and after the entry of the outsourcing unit, it specially formulated a special plan for epidemic prevention and control and an epidemic disposal plan for the outsourcing professional and technical team. Because the epidemic prevention and control program is effective, clear division of labor, responsibility in place, has been the Daye government departments of praise.
Prior to this, daye peak marketing department had already started the market's "preheating " work, understood the market situation, actively communicated with customers, and started shipping two weeks ago. Daye peak person in charge said, the impact of the new crown epidemic on the Hubei cement market is multifaceted, the restoration of market order is also a gradual process, but a long comprehensive overhaul also allows Daye peak to light, better carry out production and operation work. With the completion of the maintenance and smooth feeding, after Daye Peak will carefully organize production according to market changes, do a good job of production and sales balance, recapture the losses caused by the epidemic, and strive to complete the established annual business objectives. (Wang Yuhua Wang Xuejun)
More information
Tianjin Flemish Company Donates Anti-epidemic Materials
On the morning of July 13, Tianjin Jianfeng Flanders Pharmaceutical Technology Development Co., Ltd. donated materials to the Tianjin Development Zone Charity Association to help the development zone community fight the epidemic.
2020
08-05
In late July, leaders of the group company Jiang Xiaomeng, Yu Jianhong, Chen Tianci and Qin Xuping visited subordinate enterprises separately and sent heatstroke prevention and cooling supplies to employees working under high temperature, urging everyone to pay attention to heatstroke prevention and cooling and safe production work to ensure good physical condition.
2020
08-05
On July 17 and 18, the Group's work analysis meeting for the first half of 2020 was held at the Peak Building of the Group's headquarters to summarize and review the work in the first half of the year and make arrangements for the work in the second half of the year.
2020
08-05
The company requires to do a good job in summer safety production
The high temperature season is approaching, and the group company issued a notice a few days ago to make arrangements for safe production in summer.
2020
08-05
The company requires to do a good job in summer safety production
The high temperature season is approaching, and the group company issued a notice a few days ago to make arrangements for safe production in summer. The notice requires all subordinate units of the company to attach great importance to the work of production safety in summer, and all production and business units should hold a special meeting on production safety in summer. According to the characteristics of production in summer, they should focus on safety risk analysis for mines, outdoor operations and high-temperature posts, and implement control measures to avoid the occurrence of safety accidents such as scalding, heatstroke and electric shock. In order to further strengthen the safety production management in the high temperature season, the notice requires the main person in charge of each production and business unit to lead a team to conduct a comprehensive inspection of the production and business premises according to the characteristics of summer production; strengthen the daily safety production inspection of key posts and special posts; timely rectify the found unsafe behaviors and hidden dangers; Strengthen the management of the storage and use of flammable, explosive, dangerous chemicals and drugs; cooling measures shall be taken for the space exceeding the storage temperature limit of articles. If it is found that the electrical equipment circuit and exhaust fan circuit are aged and damaged, replace them in time and keep the grounding wire in good condition. Do a good job in checking the fire pool, pipeline water pressure and fire extinguishing equipment to ensure that the fire fighting facilities are sensitive, intact and reliable. The high temperature in summer is also a period of frequent occurrence of heatstroke and other diseases. The notice requires all units to do a good job in heatstroke prevention and cooling, implement various relevant measures, and equip necessary cooling facilities or materials such as fans, air conditioners, ice cubes and other cooling facilities or materials according to the conditions of the production site; do a good job in the distribution of heatstroke prevention drugs, supplies and cool drinks in workshops, warehouses, construction sites and other production lines; strengthen canteen management to prevent food poisoning. (this newspaper reporter)
2020
07-22
The company requires to do a good job in summer safety production
The high temperature season is approaching, and the group company issued a notice a few days ago to make arrangements for safe production in summer. The notice requires all subordinate units of the company to attach great importance to the work of production safety in summer, and all production and business units should hold a special meeting on production safety in summer. According to the characteristics of production in summer, they should focus on safety risk analysis for mines, outdoor operations and high-temperature posts, and implement control measures to avoid the occurrence of safety accidents such as scalding, heatstroke and electric shock. In order to further strengthen the safety production management in the high temperature season, the notice requires the main person in charge of each production and business unit to lead a team to conduct a comprehensive inspection of the production and business premises according to the characteristics of summer production; strengthen the daily safety production inspection of key posts and special posts; timely rectify the found unsafe behaviors and hidden dangers; Strengthen the management of the storage and use of flammable, explosive, dangerous chemicals and drugs; cooling measures shall be taken for the space exceeding the storage temperature limit of articles. If it is found that the electrical equipment circuit and exhaust fan circuit are aged and damaged, replace them in time and keep the grounding wire in good condition. Do a good job in checking the fire pool, pipeline water pressure and fire extinguishing equipment to ensure that the fire fighting facilities are sensitive, intact and reliable. The high temperature in summer is also a period of frequent occurrence of heatstroke and other diseases. The notice requires all units to do a good job in heatstroke prevention and cooling, implement various relevant measures, and equip necessary cooling facilities or materials such as fans, air conditioners, ice cubes and other cooling facilities or materials according to the conditions of the production site; do a good job in the distribution of heatstroke prevention drugs, supplies and cool drinks in workshops, warehouses, construction sites and other production lines; strengthen canteen management to prevent food poisoning. (this newspaper reporter)