April 10 Ignition Feeding Daye Peak Restart Successfully
Release time:
2020-07-22
4# February 10 Ignition Feeding
Daye Peak Successfully Restarted
News 4 10 14 58 Points, Daye Peak Cement Company Overcame the Difficulties Caused by the New Crown Epidemic, after more than 60 days of closed overhaul and renovation, the ignition and feeding were finally successful, and the official "restart " .
According to the plan before the Spring Festival, this overhaul includes technical renovation of grate cooler, replacement of rotary kiln cylinder, technical renovation of cement mill, renovation of mixed material feeding system, kiln process overhaul, etc. Due to the outbreak of new coronary pneumonia before the Spring Festival, Daye Peak is on the edge of Wuhan, the core area of the epidemic, prevention and control pressure is very great. Since the Spring Festival holiday on 1 23 , Daye Peak has started the prevention and control of the new coronary pneumonia epidemic according to the standards of the period of "SARS " in accordance with the requirements of the Group. With the change of the epidemic situation, daye peak adjusted its work plan in time according to the needs of production and operation and the prediction of the market. the original plan was to stop production and overhaul on 1 27 and postpone it to 2 . it was not until the raw materials in stock were consumed and the clinker was fully stored in the warehouse that the whole line was shut down, and maintenance was started while epidemic prevention.
According to the particularity of the long construction period, strong professionalism and many outsourcing units of this overhaul and technical renovation, Daye Peak actively coordinated with relevant departments of Daye and Baoan Town, mobilized the heads of various departments and professional personnel of the manufacturing department, and selected the civil construction team to be stationed in the factory. For projects with long overhaul time and many overlapping tasks, Daye Peak first organized personnel to conduct closed overhaul, the left-behind management personnel, mechanics and electricians dismantled the grate cooler frame by themselves, reformed the cement grinding machine, and organized the civil construction of mixed materials. After the frame of
grate cooler was removed, Daye Peak began to contact the maintenance team to enter the factory. At that time, although some progress was made in the prevention and control of the epidemic, the previously identified maintenance teams still played "retreat " . After multi-party coordination and active docking with other maintenance units, with the active cooperation of relevant departments in daye city, the first maintenance team successfully entered the factory on 2 20 . With the follow-up of various work, the number of outsourcing personnel reached 248 at the peak of maintenance work. The technical renovation project was implemented in an orderly manner as planned. The technical renovation of
grate cooler is the most important item in the technical renovation plan of Daye Peak 2020 . Due to the impact of the epidemic, the personnel of the design institute originally responsible for this work were unable to be in place for a long time. Daye Peak actively coordinated, purchased relevant materials in advance, contacted the units that had business cooperation with the company, coordinated and organized personnel to be added to the construction team, and contacted the local construction team for preliminary civil work when the design institute was unable to arrange civil work, effectively reducing the impact of the epidemic on the maintenance period.
In order to ensure the smooth progress of the maintenance work while doing a good job in epidemic prevention and control, Daye Peak departments actively cooperate, canteens do a good job in food protection, procurement departments do a good job in maintenance materials and epidemic prevention materials protection, manufacturing department arranges work in the management group, and departments arrange factory workers to use their free time to assist in cleaning up the site and carrying materials, and cooperate with the work within their capabilities. In this process, the person in charge of the relevant departments of technological transformation used the maintenance meeting every day to communicate and coordinate in advance to ensure the smooth progress of the overall construction.
During the overhaul, Daye Peak revised the five stages of the epidemic prevention and control plan according to the changes in the epidemic situation and the need for overhaul, and after the entry of the outsourcing unit, it specially formulated a special plan for epidemic prevention and control and an epidemic disposal plan for the outsourcing professional and technical team. Because the epidemic prevention and control program is effective, clear division of labor, responsibility in place, has been the Daye government departments of praise.
Prior to this, daye peak marketing department had already started the market's "preheating " work, understood the market situation, actively communicated with customers, and started shipping two weeks ago. Daye peak person in charge said, the impact of the new crown epidemic on the Hubei cement market is multifaceted, the restoration of market order is also a gradual process, but a long comprehensive overhaul also allows Daye peak to light, better carry out production and operation work. With the completion of the maintenance and smooth feeding, after Daye Peak will carefully organize production according to market changes, do a good job of production and sales balance, recapture the losses caused by the epidemic, and strive to complete the established annual business objectives. (Wang Yuhua Wang Xuejun)
More information
Editor's note: During the National Day, the "Jinhua New Observation" column of Jinhua TV Station launched a series of reports on "National Day New Observation: New Development of Old Enterprises" to understand the new developments of those old enterprises that have grown up with New China in the new era. October 3 broadcast of the "peak of the 'centennial 'ideal", about the development of the peak group and the future direction of development. The "century" ideal of the peak Jinhua TV reporter Wang Dujuan Jiang Qian host: speaking of Zhejiang Jianfeng Group Co., Ltd., Jinhua people are no stranger. The older generation of Jinhua people are more familiar with, may be the predecessor of Jianfeng Group-Jinhua Cement Factory. Open the first old photo 58 years ago, surrounded by mountains and a rice field in the middle. Old Jinhua can see at a glance that this is the Wise Temple, 8 kilometers north of Jinhua City and east of the former Zhuangtou of Luodian Town. In August 1958, the first group of pioneers came here and built Jinhua's first cement factory on a desolate hillside of 16.94 mu with a pair of hands and warm blood. From the earliest cattle-drawn ball forming machine to the electric ball forming machine, from pure manual labor to machine substitution, it took 26 years of hard work. By 1983, the annual output of peak cement reached 120000 tons, the output value was 6.75 million yuan, and the profit was 2.4 million yuan. In these 26 years, the cement plant has experienced a difficult period of the country, and the ten-year catastrophe of the "Cultural Revolution" has finally ushered in a good time of reform and opening up with tenacious vitality, laying the foundation for steady development in the future. Looking at these old pictures,
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Jianfeng won the Zhejiang Industrial Award
A few days ago, we learned from the relevant departments of Zhejiang Province that the company won the 2016 "Zhejiang Industrial Award Silver Award". Zhejiang Industrial Award was established in 2014 and is selected every two years. The purpose of carrying out the selection and commendation of the Zhejiang Industrial Awards is to thoroughly implement the "August 8 Strategy", comprehensively implement the innovation-driven development strategy, speed up the industrial transformation and upgrading with the "four for three" as the starting point, and commend the adherence to the scientific concept of development. adhere to industry, conscientiously fulfill social responsibilities, establish a modern enterprise system, and take a new road of industrialization with characteristics. The evaluation work is jointly organized and implemented by Zhejiang Industrial Economic Federation, Enterprise Federation, Entrepreneur Association, relevant provincial industry associations, municipal industrial economic federations, enterprise federations, entrepreneur associations, and relevant units. The award review committee is composed of relevant government departments, provincial "three committees", relevant provincial industry associations, and experts in industrial economy, management, finance, taxation, quality, environmental protection, safety, technology, and law, the participating enterprises are comprehensively evaluated from the aspects of industry demonstration role, scientific and technological innovation, economic benefits, resource utilization, environmental protection, brand strategy, product quality, production safety, social responsibility, enterprise management, human resources and so on. "The enterprises that have won the Zhejiang Industrial Award this time are all outstanding enterprises that have made significant contributions to the promotion of Zhejiang's economic development; they are all leading enterprises, backbone enterprises, and high-growth enterprises from different industries, representing the scale of Zhejiang's industrial development. The direction and leading spirit represent the highest level of Zhejiang's industrial development." According to the organizers related negative
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-30
Peak two enterprises were commended
On September 23, the launching ceremony of the 2016 Jinhua Zhejiang Shopping Festival and the 2015 Jinhua Honest Enterprise Commendation Conference were held in the urban people's square. Jianfeng Group's Jinhua Jianfeng Pharmacy Chain Co., Ltd. and Zhejiang Jianfeng International Trade Co., Ltd. were commended.
2020
07-31