Daye Jianfeng Cement Co., Ltd. Kiln End Flue Gas Desulfurization Project Completion Environmental Protection Acceptance Publicity
Release time:
2020-07-31
Daye Jianfeng Cement Co., Ltd. Kiln End Flue Gas Desulfurization Project
Completion Environmental Protection Acceptance Publicity
According to the requirements of Interim Measures for Environmental Protection Acceptance of Construction Project Completion (National Environmental Planning and Environmental Assessment [2017] No. 4 ) of the Ministry of Environmental Protection,
The environmental protection acceptance information of "Kiln End Flue Gas Desulfurization Project" of daye Jianfeng Cement Co., Ltd. is now publicized. Basic Information of
1. Project
Project Name: Kiln End Flue Gas Desulfurization Project
Project Construction Unit: Daye Jianfeng Cement Co., Ltd.
Project Construction Location: Yongguang Village, Baoan Town, daye city, nature of
Project in the existing factory area of daye Jianfeng Cement Co., Ltd: the construction content of the technical renovation
project is as follows:
This technical renovation project is mainly to build a wet desulfurization system for the kiln tail flue gas of the company's existing daily production 4000t cement clinker production line, adopting limestone - gypsum wet flue gas desulfurization process. The project covers a total area of 500m 2 , with a new construction area of about 450 m 2 . It mainly builds desulfurization complex building, flue gas system, SO 2 absorption system, limestone powder conveying and limestone slurry preparation system, process water system, gypsum dehydration system and supporting pipelines, etc. Power supply, water supply, compressed air and other public works rely on the existing plant.
Project Total Investment and Environmental Protection Investment: The total investment of the project is 1037 Yuan , all of which are environmental protection investment. The
project was commissioned by Huangshi Changjiang Environmental Engineering Design Institute to conduct an environmental impact assessment on 2017 9 . On 2017 11 16 , daye city Environmental Protection Bureau approved the document No.78 [2017]354 .
Implementation of 2. Environmental Protection Measures
The scope of this acceptance is Kiln End Flue Gas Desulfurization System and Supporting Facilities .
(1) Exhaust Gas Pollution Prevention Measures
Project Organized Exhaust Gas Emission Main Pollutants are SO 2 ; The main pollutant of unorganized exhaust gas emission is dust. In the
slurry preparation system, the processes of transportation, feeding, ash separation and silo are fully enclosed, and the pulping process is equipped with ash and dehumidification devices. The SO 2 in the waste gas of the rotary kiln is treated by limestone - gypsum method and discharged from the 110m high chimney at high altitude; the emission concentration of SO 2 and unorganized dust can meet the emission limit requirements of (GB4915-2013 ) "Comprehensive Emission Standard for Air Pollutants in Cement Industry.
(2) Water Environment Pollution Prevention and Control Measures
Project Drainage is divided into rain and sewage, and rainwater ditches (cement hardening) are set up. Rainwater at the project site enters the existing rainwater system in the plant area. Drainage ditches and water collecting tanks are built, equipped with cyclone machines and filtrate collection tanks. The wastewater is collected by the water collecting tanks and recycled for production without external discharge; A 570m 3 accident slurry tank has been built. The slurry discharged from the absorption tower during the accident will be collected in the accident slurry tank and recycled to the absorption tower without being discharged outside, thus having little impact on the outside world.
(3) noise prevention measures
project noise mainly comes from production equipment such as fans and water pumps, equipment is low noise equipment; The fans and pumps are all placed in closed compartments, and measures such as vibration reduction, noise elimination and distance attenuation are taken.
(4) Solid Waste Pollution Prevention Measures
The solid wastes discharged during the operation period of the project are mainly domestic garbage and desulfurization gypsum. A standardized temporary storage room for solid waste is built on the first floor of the desulfurization station. The dehydrated gypsum is collected by the temporary storage room and regularly transported to the gypsum storage yard in the plant area. As raw material, it enters the cement mill and is not discharged. Domestic waste is uniformly removed and transported by the local environmental protection department for centralized treatment.
3. Acceptance Survey Results
(I) Construction Period
During the construction period, various environmental protection measures were implemented with little impact on the surrounding environment.
(II) operation period
1 , acceptance monitoring condition
acceptance monitoring period (2019 3 July 21-22 ; 2019 172 5 March 27-28 ), the project is operating normally, design and production of cement 4000t/d ; The actual 3 September 21-22 day, 5 March 27-28 day production load all reached above 82% of , the completion acceptance monitoring condition was greater than 75% of , and the monitoring data were valid.
and Waste Gas
3 monitoring points were set up at the factory boundary to monitor the unorganized particulate matter emitted by the project for two days. The maximum concentration of unorganized particulate matter emitted from the factory boundary is lower than 0.5 mg/m 3 , does not exceed the unorganized emission limit of in table of "cement industry comprehensive emission standard for air pollutants " (GB 4915-2013 ).
During this acceptance monitoring period, SO 219 in the inlet and outlet exhaust gas of the desulfurization tower at the end of the rotary kiln was monitored. The monitoring results show that the average desulfurization efficiency of the desulfurization tower at the end of the rotary kiln reaches above 91% in the desulfurization 223. in the exhaust gas at the outlet of the exhaust pipe
More information
In the eastern corner of the production area of Jianfeng Health Technology Company, there is a very inconspicuous building. From below, only a few pipes of uneven thickness can be seen on the top and the slogan "Focus on Environmental Protection and Promote Sustainable Development" with red letters on the yellow background on the stainless steel guardrail. Walking up, you can only see several closed pools and a small room with stacks of documents, test tubes, glass bottles and other testing tools on the table. This is the peak and healthy sewage treatment station. The production sewage of the whole factory area is concentrated here. After adjustment (PH adjustment), pre-acidification, anaerobic, anoxic, aerobic (aeration), precipitation and other links, it is discharged into the pipe network after reaching the special discharge standard. Yin Zhiwu, executive deputy general manager of Jianfeng Health, said that because the sewage treatment station in Wucheng District has not yet been built, Jianfeng Health has not yet been able to achieve pipe discharge, and the relevant national laws have strict requirements on the discharge of water pollutants from the extraction pharmaceutical industry. Sewage discharge must reach a special discharge limit, that is, chemical oxygen demand (COD) must be less than 50 mg/L. Enterprise development and environmental protection are both the concept of peak health since its establishment. In March this year, on the basis of the original environmental protection facilities, Jianfeng Health carried out technical renovation of waste gas collection and treatment facilities, and at the same time installed a sealing cover on the sewage treatment station to realize the closed collection of waste gas. Since the trial operation of this facility in mid-May, the overall effect has been obvious. The original treatment tank would emit an unpleasant smell during work, but now the smell has been significantly reduced. Compared with the young enterprise of peak health, the relatively "older" peak pharmaceutical has more experience in sewage treatment and environmental protection. Akihama
2020
07-31
2016 Annual General Meeting of Shareholders
News from our newspaper On May 19, the on-site meeting of Jianfeng Group's 2016 Annual General Meeting of Shareholders was held in Conference Room 314 of Jianfeng Building to deliberate and pass the "2016 Annual Report on the Work of the Board of Directors" and other proposals. The meeting was convened by the board of directors of Jianfeng Group and chaired by Chairman Jiang Xiaomeng. A total of 6 shareholders and proxies attended the meeting, and the total number of voting shares held by them was 55,604,815, accounting for 16.16 of the total voting shares of the company. Some directors, supervisors and secretary of the board of directors of the company attended the meeting, and some senior managers attended the meeting as nonvoting delegates. The meeting was held and voted on by a combination of on-site voting and online voting, it deliberated and passed nine proposals, including the 2016 Work Report of the Board of Directors, the 2016 Work Report of the Board of Supervisors, the 2016 Financial Final Accounts Report, the 2016 Profit Distribution Proposal, the Proposal to Hire the Company's 2017 Audit Institution, the Proposal to Provide Guarantee to Holding Subsidiaries, the 2016 Annual Report and its Summary, the Election of Mr. Huang Sujian as Director of the Company and the Election of Mr. Chen Tianci as Supervisor of the Company. (Zhou Hengbin)
2020
07-31
2016 Annual General Meeting of Shareholders
News from our newspaper On May 19, the on-site meeting of Jianfeng Group's 2016 Annual General Meeting of Shareholders was held in Conference Room 314 of Jianfeng Building to deliberate and pass the "2016 Annual Report on the Work of the Board of Directors" and other proposals. The meeting was convened by the board of directors of Jianfeng Group and chaired by Chairman Jiang Xiaomeng. A total of 6 shareholders and proxies attended the meeting, and the total number of voting shares held by them was 55,604,815, accounting for 16.16 of the total voting shares of the company. Some directors, supervisors and secretary of the board of directors of the company attended the meeting, and some senior managers attended the meeting as nonvoting delegates. The meeting was held and voted on by a combination of on-site voting and online voting, it deliberated and passed nine proposals, including the 2016 Work Report of the Board of Directors, the 2016 Work Report of the Board of Supervisors, the 2016 Financial Final Accounts Report, the 2016 Profit Distribution Proposal, the Proposal to Hire the Company's 2017 Audit Institution, the Proposal to Provide Guarantee to Holding Subsidiaries, the 2016 Annual Report and its Summary, the Election of Mr. Huang Sujian as Director of the Company and the Election of Mr. Chen Tianci as Supervisor of the Company. (Zhou Hengbin)
2020
07-31
2016 Annual General Meeting of Shareholders
News from our newspaper On May 19, the on-site meeting of Jianfeng Group's 2016 Annual General Meeting of Shareholders was held in Conference Room 314 of Jianfeng Building to deliberate and pass the "2016 Annual Report on the Work of the Board of Directors" and other proposals. The meeting was convened by the board of directors of Jianfeng Group and chaired by Chairman Jiang Xiaomeng. A total of 6 shareholders and proxies attended the meeting, and the total number of voting shares held by them was 55,604,815, accounting for 16.16 of the total voting shares of the company. Some directors, supervisors and secretary of the board of directors of the company attended the meeting, and some senior managers attended the meeting as nonvoting delegates. The meeting was held and voted on by a combination of on-site voting and online voting, it deliberated and passed nine proposals, including the 2016 Work Report of the Board of Directors, the 2016 Work Report of the Board of Supervisors, the 2016 Financial Final Accounts Report, the 2016 Profit Distribution Proposal, the Proposal to Hire the Company's 2017 Audit Institution, the Proposal to Provide Guarantee to Holding Subsidiaries, the 2016 Annual Report and its Summary, the Election of Mr. Huang Sujian as Director of the Company and the Election of Mr. Chen Tianci as Supervisor of the Company. (Zhou Hengbin)
2020
07-30
Jianfeng Pharmaceutical Won Advanced Collective of Municipal Red Cross Humanitarian Promotion Award
On April 24, the Red Cross Society of Jinhua issued a circular commending the advanced units and individuals of the 2016 Red Cross Humanitarian Promotion Award. Peak Pharmaceutical Company won the Red Cross Humanitarian Promotion Award for Advanced Collective. The Red Cross is a social relief organization engaged in humanitarian work, with the purpose of carrying forward the spirit of humanity, fraternity and dedication, protecting human life and health, and promoting the cause of peace and progress of mankind. As a socially responsible enterprise, Jianfeng Pharmaceutical has always attached importance to public welfare and charity work, vigorously promoted the spirit of the Red Cross, and vigorously supported the work of the Red Cross with practical actions. In September 2016, at the theme publicity activity of "World First Aid Day" and the opening ceremony of the municipal Red Cross emergency rescue station (point), Huang Jinlong, deputy general manager of the group company and general manager of the pharmaceutical company, donated 6 AEDs known as "life-saving artifact" to the Red Cross on behalf of Jianfeng Pharmaceutical, it is equipped with six Red Cross emergency rescue service stations (points), namely, Jinhua high-speed railway station, sports center, cultural center, Shuanglong scenic spot, Siping village scenic spot and Suoyuan village scenic spot. The configuration of AED equipment has played a very good role in improving the emergency rescue capacity of Jinhua's key locations, and has been affirmed by the Red Cross and related units. (Spike Pharmaceuticals)
2020
07-31
Jingmai Airport Test Flight Successfully Runway Cement Spike Manufacturing
On April 7, a Boeing 737-700 aircraft of China Eastern Airlines Yunnan took off from Kunming. After completing two flight test subjects, it landed safely at Lancang Jingmai Airport. This not only marked the basic completion of the airport flight area, The official start of the test flight also marked that the "Peak" brand airport runway cement passed the first "final exam". Lancang Jingmai Airport is a major project with milestone significance in the history of Pu'er transportation construction. Since then, an air corridor connecting southwest Yunnan and Southeast Asia has been added between Kunming and Pu'er, which will greatly promote the development and utilization of tourism resources in Lancang, Menglian and Ximeng "Pu'er Green Triangle" area, and promote the sustainable development of local economy and society; it is of great significance to strengthen the city's national defense construction, maintain border stability, promote national unity, improve emergency rescue capabilities, and promote Pu'er's integration into the country's "Belt and Road" construction. Since the start of the construction of the airport, Yunnan Jianfeng has been paying close attention to it, organizing technical research and repeated tests, and finally produced high-quality airport runway special cement, and with excellent product quality, superior product performance and high-quality service, it has become a runway for Lancang Airport. Cement manufacturer. This not only fills the gap of "peak" airport special cement, but also is of great significance to promote the "peak" brand and improve the market influence of enterprises. It is understood that Jingmai Airport is initially confirmed to be officially opened to traffic at the end of May. (Li Liangping)
2020
07-31