Huang Ping Project Main Bidding Perfect
Release time:
2020-07-22
Huang Ping Project Main Bidding Perfect Closing
News After more than 20 working days of intense and busy, 3# October 4 , the bidding for mining, construction and main equipment of Jianfeng Huang Ping Cement Project finally came to an end. Among them, the main equipment bidding, under the premise of ensuring equipment performance and supplier services, the bid price is generally about 20% lower than the quotation, which is a good start for project construction.
1 In June, with the preparation team stationed in Huang Ping, while handling various handovers, part of the preparatory work for the project construction was also carried out one after another. The highlight was the bidding for mining, construction and main equipment, and the bidding for equipment was the top priority related to the normal operation of enterprises in the future. While most employees are happily preparing for the New Year, the bidding for mining and construction has been completed. 2 August 12 , the first day of work after the Spring Festival, the bidding for the main equipment also began in an orderly manner.
As the production equipment of cement project is worth hundreds of millions of dollars, in order to ensure that the equipment bidding can have a relatively ideal cost performance, the bidding team divided all the equipment into several project packages such as kiln system, mill, mine crusher, hoist, kiln head and kiln tail dust collector, powder separator, packaging machine, etc., and issued invitations to equipment suppliers with certain strength, equipment manufacturing level and strong professional and technical ability in the industry. In the actual bidding process, the bidding units of each project package are more than 3 , and some projects have seven or eight units participating in the competition. After repeated negotiations and bargaining, most of the equipment won the bid at the lowest price, and the winning price was generally lower than the initial price by more than 20% , which will greatly save the equipment procurement cost.
Full and meticulous preparatory work is the basis for the equipment bidding to achieve the desired results. Before the formal bidding, the bidding team made a comprehensive investigation on the production unit, operation quality and market price of the relevant equipment, so as to have a bottom in mind. During the bidding process, the project designer is invited to participate in the bid evaluation and provide professional opinions on the specifications, models, performance, and advancement of the equipment. When the winning bidder is finally determined, it will not engage in "price-only theory" while ensuring that the procurement cost is reduced. For equipment manufacturers with obvious quality advantages or long-term cooperation, it will also conduct subsequent spare parts procurement, management and technical services. Comprehensive consideration, give appropriate priority. The leaders of the group company said that the bidding not only made a good start for the construction of the Huangping project, but the methods and experience are also worth learning from other units. (this newspaper reporter)
More information
Tianjin Flemish Company Donates Anti-epidemic Materials
On the morning of July 13, Tianjin Jianfeng Flanders Pharmaceutical Technology Development Co., Ltd. donated materials to the Tianjin Development Zone Charity Association to help the development zone community fight the epidemic.
2020
08-05
In late July, leaders of the group company Jiang Xiaomeng, Yu Jianhong, Chen Tianci and Qin Xuping visited subordinate enterprises separately and sent heatstroke prevention and cooling supplies to employees working under high temperature, urging everyone to pay attention to heatstroke prevention and cooling and safe production work to ensure good physical condition.
2020
08-05
On July 17 and 18, the Group's work analysis meeting for the first half of 2020 was held at the Peak Building of the Group's headquarters to summarize and review the work in the first half of the year and make arrangements for the work in the second half of the year.
2020
08-05
The company requires to do a good job in summer safety production
The high temperature season is approaching, and the group company issued a notice a few days ago to make arrangements for safe production in summer.
2020
08-05
The company requires to do a good job in summer safety production
The high temperature season is approaching, and the group company issued a notice a few days ago to make arrangements for safe production in summer. The notice requires all subordinate units of the company to attach great importance to the work of production safety in summer, and all production and business units should hold a special meeting on production safety in summer. According to the characteristics of production in summer, they should focus on safety risk analysis for mines, outdoor operations and high-temperature posts, and implement control measures to avoid the occurrence of safety accidents such as scalding, heatstroke and electric shock. In order to further strengthen the safety production management in the high temperature season, the notice requires the main person in charge of each production and business unit to lead a team to conduct a comprehensive inspection of the production and business premises according to the characteristics of summer production; strengthen the daily safety production inspection of key posts and special posts; timely rectify the found unsafe behaviors and hidden dangers; Strengthen the management of the storage and use of flammable, explosive, dangerous chemicals and drugs; cooling measures shall be taken for the space exceeding the storage temperature limit of articles. If it is found that the electrical equipment circuit and exhaust fan circuit are aged and damaged, replace them in time and keep the grounding wire in good condition. Do a good job in checking the fire pool, pipeline water pressure and fire extinguishing equipment to ensure that the fire fighting facilities are sensitive, intact and reliable. The high temperature in summer is also a period of frequent occurrence of heatstroke and other diseases. The notice requires all units to do a good job in heatstroke prevention and cooling, implement various relevant measures, and equip necessary cooling facilities or materials such as fans, air conditioners, ice cubes and other cooling facilities or materials according to the conditions of the production site; do a good job in the distribution of heatstroke prevention drugs, supplies and cool drinks in workshops, warehouses, construction sites and other production lines; strengthen canteen management to prevent food poisoning. (this newspaper reporter)
2020
07-22
The company requires to do a good job in summer safety production
The high temperature season is approaching, and the group company issued a notice a few days ago to make arrangements for safe production in summer. The notice requires all subordinate units of the company to attach great importance to the work of production safety in summer, and all production and business units should hold a special meeting on production safety in summer. According to the characteristics of production in summer, they should focus on safety risk analysis for mines, outdoor operations and high-temperature posts, and implement control measures to avoid the occurrence of safety accidents such as scalding, heatstroke and electric shock. In order to further strengthen the safety production management in the high temperature season, the notice requires the main person in charge of each production and business unit to lead a team to conduct a comprehensive inspection of the production and business premises according to the characteristics of summer production; strengthen the daily safety production inspection of key posts and special posts; timely rectify the found unsafe behaviors and hidden dangers; Strengthen the management of the storage and use of flammable, explosive, dangerous chemicals and drugs; cooling measures shall be taken for the space exceeding the storage temperature limit of articles. If it is found that the electrical equipment circuit and exhaust fan circuit are aged and damaged, replace them in time and keep the grounding wire in good condition. Do a good job in checking the fire pool, pipeline water pressure and fire extinguishing equipment to ensure that the fire fighting facilities are sensitive, intact and reliable. The high temperature in summer is also a period of frequent occurrence of heatstroke and other diseases. The notice requires all units to do a good job in heatstroke prevention and cooling, implement various relevant measures, and equip necessary cooling facilities or materials such as fans, air conditioners, ice cubes and other cooling facilities or materials according to the conditions of the production site; do a good job in the distribution of heatstroke prevention drugs, supplies and cool drinks in workshops, warehouses, construction sites and other production lines; strengthen canteen management to prevent food poisoning. (this newspaper reporter)
2020
07-31