Two Cement Enterprises Busy with Spring Maintenance
Release time:
2020-07-22
Off-season Maintenance Peak Season Operation
Two Cement Enterprises Busy in Spring Maintenance
News As the saying goes, "A Year's Plan lies in Spring". Just after the Spring Festival, two cement enterprises, Daye Peak and Yunnan Peak, have been engaged in intensive maintenance to prepare for the normal production and sales in 2019 .
2 July 9 , the fifth day of the first month of the lunar calendar, daye peak 2019 overhaul kicked off in the spring rain. This overhaul covers mine crushing, raw material roller, kiln head and kiln tail, coal mill, cement mill and packaging system, etc. It covers a wide range of points. At the same time, it is also interspersed with technical renovation projects such as kiln head electricity changing bags, dust control of cement delivery system, mineral powder scale, etc. In order to ensure the quality of maintenance and technical transformation work, Daye Peak planned ahead of time, organized relevant personnel of electrical, mechanical and technological specialties to sort out and discuss in advance, formulated detailed maintenance and technical transformation plans, identified special potential safety hazards and formulated preventive measures for each maintenance content. Before the formal overhaul, Daye Jianfeng Environmental Safety Department signed safety responsibility letters with 12 teams participating in the overhaul, reviewed the qualifications and operator certificates of the participating teams one by one, and organized relevant safety knowledge training. During the maintenance period, in addition to holding maintenance meetings every day, reporting the progress of each maintenance point by each specialty, and connecting with the maintenance unit, daye peak also specially set up a safety inspection team. the company's competent leaders and responsible persons of various departments will follow up on the spot, monitor the maintenance process, strictly grasp habitual violations, power outage, dangerous operations and employees' fluke psychology, and require all maintenance units to gather wastes, and clear the personnel after the maintenance, to ensure that the work is carried out in a safe and orderly manner.
Yunnan Peak started to work out the maintenance plan before the Spring Festival. The maintenance started from 2 August 15 , mainly including limestone crushing to preheater castable, raw material mill, clinker crushing and other production links and coal vertical mill, grate cooler, cement mill and other major equipment. At the beginning of the formulation of the plan, safety was put first in each link, and a safety guarantee responsibility letter was signed with each construction unit, and a responsibility target assessment agreement was signed with the construction unit on the construction quality, progress, and completion time limit of each link. The supervision and inspection responsibilities of relevant departments have also made clear requirements.
It is understood that in order to ensure market stability during the overhaul period, the two cement companies insisted on starting up production and stocking during the Spring Festival to ensure sufficient inventory. At present, the maintenance work of the two enterprises is progressing smoothly. Yunnan peak has completed the maintenance work and ignited this afternoon. Daye peak maintenance is expected to end in early 3 . (Wang Yuhua Shi Zhangliang Lu Meiyan Shi Wen Ting Zhou Shaohe)
More information
Editor's note: During the National Day, the "Jinhua New Observation" column of Jinhua TV Station launched a series of reports on "National Day New Observation: New Development of Old Enterprises" to understand the new developments of those old enterprises that have grown up with New China in the new era. October 3 broadcast of the "peak of the 'centennial 'ideal", about the development of the peak group and the future direction of development. The "century" ideal of the peak Jinhua TV reporter Wang Dujuan Jiang Qian host: speaking of Zhejiang Jianfeng Group Co., Ltd., Jinhua people are no stranger. The older generation of Jinhua people are more familiar with, may be the predecessor of Jianfeng Group-Jinhua Cement Factory. Open the first old photo 58 years ago, surrounded by mountains and a rice field in the middle. Old Jinhua can see at a glance that this is the Wise Temple, 8 kilometers north of Jinhua City and east of the former Zhuangtou of Luodian Town. In August 1958, the first group of pioneers came here and built Jinhua's first cement factory on a desolate hillside of 16.94 mu with a pair of hands and warm blood. From the earliest cattle-drawn ball forming machine to the electric ball forming machine, from pure manual labor to machine substitution, it took 26 years of hard work. By 1983, the annual output of peak cement reached 120000 tons, the output value was 6.75 million yuan, and the profit was 2.4 million yuan. In these 26 years, the cement plant has experienced a difficult period of the country, and the ten-year catastrophe of the "Cultural Revolution" has finally ushered in a good time of reform and opening up with tenacious vitality, laying the foundation for steady development in the future. Looking at these old pictures,
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Jianfeng won the Zhejiang Industrial Award
A few days ago, we learned from the relevant departments of Zhejiang Province that the company won the 2016 "Zhejiang Industrial Award Silver Award". Zhejiang Industrial Award was established in 2014 and is selected every two years. The purpose of carrying out the selection and commendation of the Zhejiang Industrial Awards is to thoroughly implement the "August 8 Strategy", comprehensively implement the innovation-driven development strategy, speed up the industrial transformation and upgrading with the "four for three" as the starting point, and commend the adherence to the scientific concept of development. adhere to industry, conscientiously fulfill social responsibilities, establish a modern enterprise system, and take a new road of industrialization with characteristics. The evaluation work is jointly organized and implemented by Zhejiang Industrial Economic Federation, Enterprise Federation, Entrepreneur Association, relevant provincial industry associations, municipal industrial economic federations, enterprise federations, entrepreneur associations, and relevant units. The award review committee is composed of relevant government departments, provincial "three committees", relevant provincial industry associations, and experts in industrial economy, management, finance, taxation, quality, environmental protection, safety, technology, and law, the participating enterprises are comprehensively evaluated from the aspects of industry demonstration role, scientific and technological innovation, economic benefits, resource utilization, environmental protection, brand strategy, product quality, production safety, social responsibility, enterprise management, human resources and so on. "The enterprises that have won the Zhejiang Industrial Award this time are all outstanding enterprises that have made significant contributions to the promotion of Zhejiang's economic development; they are all leading enterprises, backbone enterprises, and high-growth enterprises from different industries, representing the scale of Zhejiang's industrial development. The direction and leading spirit represent the highest level of Zhejiang's industrial development." According to the organizers related negative
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-30
Peak two enterprises were commended
On September 23, the launching ceremony of the 2016 Jinhua Zhejiang Shopping Festival and the 2015 Jinhua Honest Enterprise Commendation Conference were held in the urban people's square. Jianfeng Group's Jinhua Jianfeng Pharmacy Chain Co., Ltd. and Zhejiang Jianfeng International Trade Co., Ltd. were commended.
2020
07-31