"No, come and see!" In the early morning of 8# September , before dawn, the silence in the central control room of daye peak was broken. It turned out that the water pipe pressure detection device suddenly detected an abnormality: the pressure of the production supply water pipe from Baoan Lake to the factory area plummeted!
In order to ensure the normal operation of the production line, the plant decided to immediately stop the supply of domestic water. However, if the production of the kiln is stopped due to the leakage of the pipeline, it will bring huge economic losses to the enterprise, and the repair work is imminent.
Chen Changfa, Gao Guoli and Huang Shuisong of the Waste Heat Power Generation Department immediately formed an emergency repair team and set off as soon as possible. Everyone walked along the lines buried by the water pipes to carefully search and eliminate. After several hours of investigation, the leak was finally found around 8 : 30. However, this section of the pipeline, which is located at the junction of the fish pond and Baoan Lake, is "in danger". It is laid in the water, and the water level is nearly one person high, which brings great difficulties to the emergency repair team. After some discussion, the emergency repair team decided to contact the company to arrange for the pump to pump water. Taking advantage of this gap, the emergency repair team carried out the cofferdam. After the pump is in place, as the water level slowly drops, the seeping water pipe appears. Chen Changfa immediately went into the water to repair, remove screws and install Haff Festival. Everything seemed to be developing according to the expected progress. However, at this moment, a stream of water surged in, almost washed down the repair workers, and the temporary dam on this side of the fish pond "burst. The water swept in, flooding the pipes in an instant and destroying previous efforts. Everyone had to come up from the water first to discuss countermeasures.
"Get in the water!" At a loss, I don't know who shouted, and all the repair workers began to rush into the water again. The water is mixed with silt, weeds and other debris, and the repair personnel carry forward the spirit of not being afraid of hardship, not afraid of tiredness, and continuous combat, and persist in working in the water. However, the work clothes soaked in water swell like lanterns, and the huge buoyancy makes it difficult to maintain balance in the water. When screwing the screw, the whole person swings in the water like an oar, making it difficult to find the focus.
Faced with this situation, Chen Changfa took off his clothes and continued to fight in the water shirtless. When his companions saw this, they also joined the ranks. Tao Yecheng, assistant to the general manager who came to the scene to learn about the situation, said: "Put on your clothes quickly. It's easy to get sunburned in such a big sun." But wearing clothes seriously restricts the work. This is a battle against time, and we must not lose. In the end, Chen Changfa decided to continue to strip and rescue. He and the workers had the scorching sun on their heads until 4 : 30 p. m., and finally ruled out the danger. After landing, everyone's skin was red from the sun and felt a burning pain at the touch.
The most touching thing is Gao Guoli. He was accidentally scalded two days ago and had several fist-sized scars on his legs. After several hours of soaking, the wound showed signs of inflammation, but he did not complain at all and persisted until the repair was over.
After a day of "bathing water" fighting, the water pipe failure of Baoan Lake was eliminated, the production line resumed normal operation, and the water consumption of the factory employees began to recover. Perhaps for many people who do not know, this is just a very common water cut, but for the waste heat power generation department, they are like soldiers, winning this fierce battle with time. (Fonz Luo Dengxiang)
More information
The Sixth Plenary Session of the 18th Central Committee of the Communist Party of China was held in Beijing from October 24 to 27. It reviewed and approved the "Several Guidelines on Political Life within the Party under the New Situation" and the "Regulations on Inner-Party Supervision of the Communist Party of China. On November 22, the party committee of the group company successively held party committee and branch secretary meetings to learn the spirit of the sixth Plenary session of the 18th CPC Central Committee and put forward requirements for organizational construction and party member management. At the branch secretary meeting, Jiang Xiaomeng, secretary of the party committee of the group company, preached the main contents of "some guidelines on Inner-Party political Life under the New situation" and "regulations on Inner-Party Supervision of the Communist Party of China. He pointed out that seeking truth from facts, integrating theory with practice, keeping close ties with the masses, criticizing and self-criticism, democratic centralism, and strict party discipline are the basic norms and working principles of inner-party political life accumulated by the Communist Party of China for several generations. In the new social environment, some party members and cadres have bred some unhealthy atmosphere, which has damaged the image and interests of the party, the Sixth Plenary Session of the 18th Central Committee of the Communist Party of China proposed to strengthen and standardize the political life within the party, take the party constitution as the foundation, adhere to the party's political line, ideological line, organizational line and mass line, strive to enhance the political, contemporary, principled and fighting nature of the party's political life, and strive to enhance the party's ability of self purification, self improvement, self innovation and self improvement, Efforts should be made to improve the party's leadership and governance level, efforts should be made to safeguard the authority of the Party Central Committee, ensure the unity and unity of the party, maintain the advanced nature and purity of the party, and strive to form a centralized, democratic and disciplined party in the whole party
2020
07-31
Jinxi plant environmental protection facilities through the completion of acceptance
On November 1, Jianfeng Pharmaceutical Jinxi Pharmaceutical Factory successfully obtained the approval from Zhejiang Environmental Protection Department that the environmental protection facilities of the project passed the completion acceptance, and a key work of Jianfeng Pharmaceutical in 2016 came to an end. Jianfeng Pharmaceutical's annual output of 35 tons of cephalosporins, anti-tumor drugs and other raw material production lines and various preparation production lines technological transformation projects started construction in Jinxi Development Zone in October 2012 and were almost completed in September 2015. The construction of the project strictly abided by the "three simultaneous" system of environmental protection, conscientiously implemented the requirements in the environmental impact assessment report and its approval documents, and invested 19.34 million yuan in environmental protection facilities. The plant has basically realized the separation of clean and sewage. A new wastewater treatment system with a daily treatment capacity of 700 cubic meters and a "physical, chemical and biochemical" treatment process has been built, and an online monitoring device networked with the environmental protection department has been installed. All kinds of production wastewater, public works wastewater and domestic sewage are treated by the wastewater station and sent to Jinxi Sewage Treatment Plant for centralized treatment; there is an RTO regenerative incineration device of 10000 cubic meters per hour and a centralized treatment device of 4000 cubic meters per hour for chlorine-containing organic waste gas. All kinds of waste gas are discharged after collection and treatment. In October 2015, with the approval of Jinhua Economic and Technological Development Zone Branch of Jinhua Environmental Protection Bureau, the trial production of Jinxi project was carried out. After more than half a year of operation, in early July 2016, Zhejiang Environmental Monitoring Center Station carried out completion acceptance monitoring of environmental protection treatment facilities such as waste water and waste gas of Jinxi Pharmaceutical Factory, and issued a completion acceptance monitoring report of environmental protection facilities at the end of August.
2020
07-31
Jinxi plant environmental protection facilities through the completion of acceptance
On November 1, Jianfeng Pharmaceutical Jinxi Pharmaceutical Factory successfully obtained the approval from Zhejiang Environmental Protection Department that the environmental protection facilities of the project passed the completion acceptance, and a key work of Jianfeng Pharmaceutical in 2016 came to an end. Jianfeng Pharmaceutical's annual output of 35 tons of cephalosporins, anti-tumor drugs and other raw material production lines and various preparation production lines technological transformation projects started construction in Jinxi Development Zone in October 2012 and were almost completed in September 2015. The construction of the project strictly abided by the "three simultaneous" system of environmental protection, conscientiously implemented the requirements in the environmental impact assessment report and its approval documents, and invested 19.34 million yuan in environmental protection facilities. The plant has basically realized the separation of clean and sewage. A new wastewater treatment system with a daily treatment capacity of 700 cubic meters and a "physical, chemical and biochemical" treatment process has been built, and an online monitoring device networked with the environmental protection department has been installed. All kinds of production wastewater, public works wastewater and domestic sewage are treated by the wastewater station and sent to Jinxi Sewage Treatment Plant for centralized treatment; there is an RTO regenerative incineration device of 10000 cubic meters per hour and a centralized treatment device of 4000 cubic meters per hour for chlorine-containing organic waste gas. All kinds of waste gas are discharged after collection and treatment. In October 2015, with the approval of Jinhua Economic and Technological Development Zone Branch of Jinhua Environmental Protection Bureau, the trial production of Jinxi project was carried out. After more than half a year of operation, in early July 2016, Zhejiang Environmental Monitoring Center Station carried out completion acceptance monitoring of environmental protection treatment facilities such as waste water and waste gas of Jinxi Pharmaceutical Factory, and issued a completion acceptance monitoring report of environmental protection facilities at the end of August.
2020
07-31
Jinxi plant environmental protection facilities through the completion of acceptance
On November 1, Jianfeng Pharmaceutical Jinxi Pharmaceutical Factory successfully obtained the approval from Zhejiang Environmental Protection Department that the environmental protection facilities of the project passed the completion acceptance, and a key work of Jianfeng Pharmaceutical in 2016 came to an end. Jianfeng Pharmaceutical's annual output of 35 tons of cephalosporins, anti-tumor drugs and other raw material production lines and various preparation production lines technological transformation projects started construction in Jinxi Development Zone in October 2012 and were almost completed in September 2015. The construction of the project strictly abided by the "three simultaneous" system of environmental protection, conscientiously implemented the requirements in the environmental impact assessment report and its approval documents, and invested 19.34 million yuan in environmental protection facilities. The plant has basically realized the separation of clean and sewage. A new wastewater treatment system with a daily treatment capacity of 700 cubic meters and a "physical, chemical and biochemical" treatment process has been built, and an online monitoring device networked with the environmental protection department has been installed. All kinds of production wastewater, public works wastewater and domestic sewage are treated by the wastewater station and sent to Jinxi Sewage Treatment Plant for centralized treatment; there is an RTO regenerative incineration device of 10000 cubic meters per hour and a centralized treatment device of 4000 cubic meters per hour for chlorine-containing organic waste gas. All kinds of waste gas are discharged after collection and treatment. In October 2015, with the approval of Jinhua Economic and Technological Development Zone Branch of Jinhua Environmental Protection Bureau, the trial production of Jinxi project was carried out. After more than half a year of operation, in early July 2016, Zhejiang Environmental Monitoring Center Station carried out completion acceptance monitoring of environmental protection treatment facilities such as waste water and waste gas of Jinxi Pharmaceutical Factory, and issued a completion acceptance monitoring report of environmental protection facilities at the end of August.
2020
07-30
Daye Jianfeng Safety Standard was awarded as the only award-winning enterprise in daye city in 2015.
Due to the achievements made in the establishment of secondary safety production standardization, daye peak cement company recently received a special award of 200000 yuan from daye municipal government. In order to encourage industrial and commercial enterprises in the region to improve their production safety, daye municipal government set up a special fund in 2015, stipulating that 200000 yuan will be awarded to those who pass the secondary safety standardization review before December 31, 2015. It is understood that among the industrial and commercial enterprises in daye city, there were 4 enterprises that applied for and passed the examination in 2015, but only daye peak passed the examination before December. Therefore, Daye Peak has become the only enterprise that has won the special award for the establishment of the safety standard in Daye City in 2015. (Ye Meifang)
2020
07-31
Two Cement Enterprises Start to Implement "Big Patrol Inspection"
With the change of the competition situation in the industry, the profit space of cement production enterprises has been greatly squeezed. Reducing costs and increasing efficiency and job optimization have become the inevitable choice to improve the enterprise's own development ability and enhance the core competitiveness. In accordance with the requirements of the group company to realize the transformation from extensive management to lean management, combined with the advanced experience of peer enterprises, recently, Yunnan peak, daye peak two enterprises have implemented "big inspection" to promote the overall optimization of posts. On November 1, daye peak post inspection officially started full operation, starting from the limestone storage yard at the source of the production line to the cement storage. the original 15 posts were merged, and the best experienced mechanics, electricians and post workers were transferred to form a large inspection class, which was mainly responsible for on-site emergency disposal and post routine maintenance to ensure the normal production of the whole production line. In order to ensure the smooth implementation of the large-scale inspection, daye peak management team has repeatedly communicated and discussed with the heads of relevant workshops and departments, and held a special workshop post optimization promotion meeting in September to clarify objectives and responsibilities, formulate implementation steps, and do a lot of preparatory work. At the kick-off meeting for the implementation of the large-scale inspection on October 31, Zhang Fengliang asked daye peak employees to recognize the current situation of serious cement overcapacity and cruel market competition, understand the necessity of implementing the large-scale inspection, and asked the workshop leaders to do a good job in training and guiding the employees, shorten the transition period, normalize the operation of the large-scale inspection as soon as possible, and at the same time, managers should also change their working ideas and concepts and do a good job in full-time, strengthen the inspection, overhaul and maintenance of the regular day shift, and find and solve the problems existing in the equipment and process in time.