Announcement on the Subsidiary's Receipt of the Decision of the Environmental Protection Department Ordering to Stop Production and Remediation
Release time:
2020-08-05
Securities Code: 600668 Securities Abbreviation: Jianfeng Group Announcement No.: 2018-020
Bond Abbreviation: 13 Jianfeng 02 Bond Code: 122344
Zhejiang Jianfeng Group Co., Ltd.
Announcement
of the Company's Board of Directors and all directors guarantee that there are no false records, misleading statements or major omissions in the contents of this announcement, and shall bear individual and joint liabilities for the authenticity, accuracy and completeness of its contents
Recently, Anhui Xinbeika Chemical Co., Ltd. (hereinafter referred to as "Anhui Beika"), a subsidiary of the company, received the Dongzhi County Environmental Protection Bureau's "Decision on Ordering Suspension of Production and Rectification" (
Donghuan Zit [2018] No. 04), the main contents are hereby announced as follows:1. the contents of the "Decision on Ordering to Stop Production and Rectification"
(I) Investigation and Findings of Environmental Violations
After investigation by our bureau, it is found that your company has implemented the following environmental violations: "Your company's annual output of 500
tons of acetamiprid is in production, and the valve of the gas outlet pipeline of the activated carbon adsorption tank of the waste gas treatment facility in the 201 workshop is closed, the waste gas in the tank overflows from the outlet of the sewage pipe and the inlet and outlet of activated carbon replacement, etc., and the smell on site is heavy." The above facts ofare based on evidence such as the on-site (survey) record, investigation and inquiry record, on-site photos and so on on June 22, 2018
by our bureau.The above actions of your company violate the provisions of Article 20, paragraph 2, of the the People's Republic of China Air Pollution Prevention and Control Law.
The basis and type of the (II)'s decision to suspend production for rectification
According to Item (III) of Paragraph 1 of Article 99 of the the People's Republic of China Air Pollution Prevention and Control Law, and Item (I) of Article 6 of the Measures for the Implementation of Restrictions on Production and Suspension of Production by Environmental Protection Authorities, our bureau has decided to order your company to implement suspension of production for rectification.
Implementation method and deadline for (III) shutdown rectification
1
, your company shall immediately stop production from the date of receipt of this decision, and take corrective measures to formulate and implement the rectification plan.2
. Your company shall report the rectification plan to our bureau for the record and make it public within 15 working days after receiving this decision. The rectification plan shall determine the corrective measures, the progress of the project, the guarantee of funds and the responsible personnel.3
. After your company completes the rectification task, it shall report the completion of the rectification task and the public disclosure of the rectification information to our bureau for the record within 15 working days.4
. Your company shall not have any illegal pollutant discharge during the rectification period, and shall not resume production without reporting the completion of the rectification task to our bureau for the record.The period of suspension of production for rectification is from the date of service of this decision to the date of cancellation of the suspension of production for rectification.
Our bureau will supervise your unit after the implementation of the shutdown rectification, and conduct follow-up inspection after the shutdown rectification is lifted. If your company refuses to carry out rectification as required or commits illegal acts after resuming production, our bureau will impose administrative penalties or administrative treatment in accordance with the law according to your company's illegal circumstances and environmental consequences.
Ways and Time Limit for (IV) to Apply for Administrative Reconsideration or File Administrative Litigation
If your company does not accept this decision, it may apply for administrative reconsideration to Chizhou Municipal Environmental Protection Bureau or Dongzhi County People's Government within 60 days from the date of receipt of this decision in accordance with the provisions of Article 9 of the the People's Republic of China Administrative Reconsideration Law, an administrative lawsuit may also be brought to the people's Court of Dongzhi County within six months from the date of receipt of this decision in accordance with Article 46 of the the People's Republic of China Administrative procedure Law. If an application for administrative reconsideration or an administrative lawsuit is filed, the implementation of this decision shall not be suspended.
If you do not apply for administrative reconsideration, file an administrative lawsuit, or perform this decision within the time limit, our bureau will apply to the people's court for enforcement in accordance with the law.
2. Rectification Measures
Company attached great importance to the above decision and immediately requested Anhui Beika to actively cooperate with the environmental protection department in inspection and stop illegal acts. The specific measures are as follows:
1
. In response to the incident, the company instructed Jianfeng Pharmaceutical to immediately set up an environmental protection incident emergency working group to investigate the incident and supervise the rectification; at the same time, arrange the company's production enterprises to conduct a comprehensive environmental self-examination to prevent the occurrence of similar incidents.2
, prepare a rectification plan and arrange special funds to further upgrade the existing waste gas treatment system in Beika, Anhui Province.
3. During the period of shutdown and rectification, Anhui North Carolina will be arranged to carry out annual routine equipment maintenance to ensure the normal operation of production facilities after resumption of production.
Anhui North Carolina will complete the rectification as soon as possible and report the completion of the rectification to the Environmental Protection Bureau, so as to resume normal production as soon as possible.Impact of 3. on the Company
2018
In January and August, the board of directors of the company approved that the subsidiary Zhejiang Jianfeng Pharmaceutical Co., Ltd. acquired 55% of the equity of Shanghai Beika Pharmaceutical Technology Co., Ltd. by acquiring shares and increasing capital. Anhui Beika is a wholly-owned subsidiary of Shanghai Beika Pharmaceutical Technology Co., Ltd. In May 2018, the industrial and commercial change registration and handover procedures for the investment were completed. In accordance with the "Application Guide to Enterprise Accounting Standards No. 20-Business Combinations", the Company has included Shanghai Beika Pharmaceutical Technology Co., Ltd. and its subsidiaries in the scope of the Company's consolidation since June 2018.At the end of 2017
, the company's total assets were 41.76 .1 billion yuan, and the net assets attributable to the owners of the parent company were 2.627 billion yuan. In 2017, the company realized operating income of 2.827 billion yuan and realized net profit attributable to the owners of the parent company. 0.348 billion yuan. At the end of 2017, Anhui North Card's total assets were 0.047 billion yuan and net assets were 0.012 billion yuan. Anhui North Card's annual operating income in 2017 was 0.046 billion yuan and net profit was -0.008 billion yuan. Anhui North Card's total assets were about 1.13 of the company's total assets and its operating income was about 1.63 of the company's operating income. Anhui North Card has a small impact on the Company's overall operating income and efficiency.
The company will strictly follow the "Shanghai Stock Exchange Stock Listing Rules" and other relevant requirements to do a good job of information disclosure in a timely manner. Please invest rationally and pay attention to investment risks.This is to announce
Zhejiang Jianfeng Group Co., Ltd. Board of Directors
July 5, 2018
More information
Peak re-listed China's top 100 cement production capacity Daye peak won the "smart factory leader"
On July 11-12, the 2022 China Cement Industry Summit and TOP100 Award Ceremony organized by China Cement Network, an authoritative media of China's cement industry, was held in Hangzhou. Jianfeng Group once again ranked among the top 100 cement clinker production capacity in China.
2022
08-04
On the afternoon of July 12, the party Committee of the group company held a special meeting attended by party Committee members, senior and middle-level management backbones, heads of grass-roots party organizations and all party members of the group headquarters to learn and convey the spirit of the 15th party congress of the communist party of China in Zhejiang province.
2022
07-24
On the morning of July 1, more than 40 members of the group's party committee, party members of various branches of the group headquarters, and party members of subordinate enterprise branches went to the Shuanglong Hydropower Station, the Red Education Base of Jinhua City, to receive party spirit and revolutionary tradition education.
2022
07-14
Vocational skill level identification examination!
On June 16 and 18, the theoretical and practical examinations for the determination of professional skill level in the peak pharmaceutical sector were held successively in Jinxi pharmaceutical factory. The independent identification of vocational skill level includes three occupations (types of work): pharmaceutical preparation worker, chemical inspector and organic synthesis worker, basically covering the main posts in the pharmaceutical sector, with a total of 125 employees signing up for the identification.
2022
06-21
On June 16, the Jianfeng Pharmaceutical Quality Research and Development Party Branch and the Jinhua Vocational Skills Management Service Center Party Branch held a signing ceremony in Jinxi Factory to establish a party building alliance.
2022
06-21
Jinhua Mayor Xing Zhihong to Peak Research
On the afternoon of June 1, Jinhua Mayor Xing Zhihong, Wucheng District Party Committee Secretary Gao Feng, District Mayor Hu Yuxian, and heads of the Municipal Economic and Information Bureau, Development and Reform Bureau and other departments went to the group headquarters to discuss and exchange with the leaders of the group company to understand the development of the enterprise. Solicit opinions and suggestions from enterprises on government work. After understanding the current business situation of the peak, Xing Zhihong pointed out that focus, follow the right path, frontier, steady, is the peak to long-term prosperity of the magic weapon, must continue to adhere.
2022
06-13