Behind the Luck.
Release time:
2020-08-14
"Luck"
Artificial Bezoar Workshop Reconstruction Documentary
After four months of intense work, 8# September 9 , the artificial bezoar technical renovation project of Qiubin Factory was successfully completed, 8 18 , 19 , 20 , the trial production of the first three batches of products was successfully completed. Yi Shengrong, director of the Akihama Factory, lamented, "We are lucky this time".
Good luck, this is of course a joke. To do such a big project well, luck alone is of course not enough. What really plays a decisive role is the seriousness and hard work of the project team members.
Pharmaceutical Company has many years of successful experience in producing artificial bezoar, but from the beginning of the project transformation, due to the use of raw materials, production process, process standards, and production scale are almost different, so the previous experience is not for them. Help, can only be explored from scratch through the efforts of participating construction personnel. From the beginning of the
project, the project team was formed by Yi Shengrong, director of Qiubin Factory, Yu Chengfeng, production technology department, Yan Xixia, workshop director, Fang Weiming, mechanic, and Tang Songnian, electrician. While ensuring normal production, the project began to transform. The civil engineering project of workshop
started in March 4 . The project team members divided their work according to their own fields. Fang Weiming and Tang Songnian, who were responsible for equipment selection, went to many equipment manufacturers to understand relevant information, make comparisons and prepare for bidding. Compared with the previous production, the requirements for environmental protection are higher now. When designing the artificial bezoar workshop, it was decided to adopt dust-free transportation. All equipment is connected through pipelines. In order to meet this requirement, most equipment must be customized from the manufacturer. Before the formal bidding of the equipment, the project team also held a special meeting to brainstorm and put forward opinions and suggestions on equipment selection according to the collected information and their own work experience. It has been suggested that corn starch is one of the main raw materials for the production of artificial bezoar. A lot of heat will be generated during the ball milling process. If the temperature is too high, the starch will stick together and affect the quality of the product. Although there is no requirement for this in the process standard, it can be related to the quality of the product, so when selecting the equipment, the equipment manufacturer is required to increase the cooling system for the heat dissipation problem of the ball mill. Fang Weiming said that it takes three months for general equipment manufacturers to obtain orders and provide products, but we only have more than one month, and the equipment is not stereotyped, so the two sides have communicated repeatedly many times.
Despite this, there were still some small "episodes" in the acceptance stage before the equipment entered the site ". There is a gap between the inlet and outlet of the equipment and the previous requirements, which will cause waste of raw materials. But because the construction period is very tight, the time nodes of each link are very close, if you can not enter the site on time, the whole project will be affected. This can be anxious for the project team. After communication and arrangement, it was finally decided to give the equipment manufacturer a week to revise it. After meeting the required requirements, the equipment was pulled over quickly. Other minor problems can only be to let the equipment manufacturer personnel come over and make on-site modifications.
In the trial production stage, in order to save costs, Qiubin Factory decided that the batch of products is 100 kg, while the design capacity of the equipment is 500 kg. There is no data that can be directly referred to for the process parameters such as ball mill speed, ball milling time and ball quantity. Before the trial, the members of the project team also consulted relevant production enterprises, however, the other party has only tried batch 300 kg, and has not succeeded. There are more than ten kinds of trial production schemes involved in the three parameters. Time and cost are not allowed to try multiple schemes. We can only rely on the collection and selection of indirect experience collected by project team members from various channels, and finally confirm the formation of the scheme decided to put into production. The trial production was an unexpected success. All the indexes of the three batches of trial production products passed the test. Moreover, the color, the most difficult index to control for artificial bezoar, was highly recognized by the sales agent.
The implementation of the whole project is relatively smooth, and there may be elements of luck, but behind this "luck", only the participants know how much effort and hardship they have put in. Cleaning the workshop equipment happens to be the hottest time. The weather has been more than 40 degrees for more than half a month, which makes the project team members unable to bear it. The workshop that has just been renovated is very dusty, but in order to ensure the cleaning quality, the air conditioner cannot be turned on, so it can only be cleaned under high temperature. Once out of the workshop, the whole person seems to have been soaked in water, and none of his body is dry. Moreover, his body is covered with dust. If there is something to do in the production workshop, he has to change clothes first.
Yan Xixia was impressed by one thing. The proportion and amount of balls in the ball mill will directly affect the product quality. For this reason, the two employees put 4 alumina balls of different sizes, totaling 2 tons, into small baskets one by one, and poured them into the ball mill with their bare hands for testing. The ball mill is large in size, and the feed port is above the machine. Employees holding the ball have to walk on a platform more than two meters high before they can pour in. If the ratio is not right, it has to be poured out again, cleaned, dried, and then poured in baskets again. This data alone has been tried for 3. four days. It goes up and down dozens of times a day. It is completely a physical job. Sometimes my hands shake after work. And sometimes afraid of miscounting the number of balls, employees squat down directly one by one.
Not only that, during the entire construction period from 4 to 7 February, Yu Chengfeng, Fang Weiming and Tang Songnian did not rest for a day and gave up their holidays. As long as the construction unit was present, they would have to be there. Finally, even the number of overtime days was not counted.
The end of the three batches of trial production products does not mean the end of this technological transformation project. They have a more important task, that is, to apply for GMP certification, and are now preparing for relevant materials. (Reporter Ni Yingzhen)
More information
Since the implementation of the large-scale inspection in early November 2016, Daye Jianfeng Cement Company has embarked on a comprehensive institutional adjustment and optimization, which has been carried out for more than five months. In just a few months, the internal management of Daye Peak has achieved a preliminary transformation, the process has been further straightened out, and the work efficiency has also been significantly improved. Reduce the hierarchy and further flatten the management. In the past, in order to avoid responsibilities, there were often repeated and overlapping settings in the setting of enterprise posts, and even there were cases where no one handled the accident and no one took responsibility. In order to truly realize flat management, daye peak merged the original production department, technology department, manufacturing workshop and finished product workshop to form a manufacturing department in early January this year after the implementation of large-scale inspection. Merging the former Environmental Security Department and the Comprehensive Management and Security Department to form the Environmental Security Department; The purchasing functions of the original departments were merged into the purchasing department. The functions of the infrastructure section of the former comprehensive management department were merged into the waste heat power generation department. After the adjustment of the organization, the members of the management team in charge of production also served as department managers, realizing the "sinking" of management ". Adjust and formulate the responsibility system to ensure that tasks are on duty and responsibilities are on duty. In response to changes in institutions and job settings, Daye Peak has carried out a comprehensive revision of the job responsibility system, making requirements around the key indicators of various departments and positions, and implementing "personalization" of responsibilities ". For example, the relevant indicators of mechanics focus on the consumption of machinery and materials, the operation rate of the equipment under their jurisdiction, and the failure time, and the hook for cement and clinker production has been canceled. Responsibility assessment is carried out according to post responsibilities and relevant management systems, and the assessment has been strengthened. In order to understand the actual effect of daye peak institutional reform, on March 30, the group company
2020
07-31
Group Party Committee to determine the annual work plan
The party Committee of the group company has determined its work ideas and work plan for 2017 a few days ago, and relevant work has been arranged below. In view of the current new political and economic situation and the task of enterprise transformation and development, the general requirements of the Party Committee of the Group Company for 2017 are: to thoroughly study and implement the spirit of the Sixth Plenary Session of the 18th CPC Central Committee and the series of important speeches by General Secretary Xi Jinping, the spirit of the Seventh Party Congress of Jinhua City, to closely revolve around the center of enterprise production, operation and reform and development, and to adhere to scientific development and cross-regional development as the first priority, in order to continue to carry out the study and education of "five stars striving for innovation" and "two learning and one doing", we should highlight the main line of comprehensively and strictly administering the party according to the rules, firmly establish the political awareness, overall situation awareness, core awareness and alignment consciousness of the majority of Party members and cadres, strengthen and improve the party building work in enterprises in the spirit of reform, and strive to improve the scientific, standardized and institutionalized level of Party building work in enterprises, in order to promote the scientific development of the group company, leapfrog development and harmonious development, it provides a strong political, ideological and organizational guarantee. The working idea of the Party Committee of the Group Company in 2017 is to focus on "one center", adhere to "one concept", highlight "three key points" and do a good job in "three constructions". That is: centering on the "one center" of enterprise production, operation and reform and development, we should strive to strengthen the "one concept" of "the organic unity of the party's leadership and the improvement of corporate governance"; to "thoroughly implement the main responsibility of the party committee; continue to carry out the study and education of" two learning and one doing "; and improve the system of party building work" as the "three key points", and focus on "team building and team building
2020
07-30
End of 2016 Qualification Review
According to our newspaper, the 2016 employee qualification evaluation work ended a few days ago, and 380 employees obtained new qualifications. Since the implementation of the employee qualification evaluation system in 2010, it has produced certain results in promoting employees to strengthen self-learning and improve and establish a multi-channel career development system for employees. Since the company's cement sector was included in the scope of qualification management for the first time, in accordance with the relevant regulations of the company's employee qualification management, the written examination for this review was conducted in Jinhua, Daye, and Pu'er on December 25, 2016. After professional knowledge examination, performance evaluation and comprehensive evaluation, the qualification of the corresponding grade and grade is finally determined. A total of 380 employees participated in the review, including 40 in management, 59 in technology and 281 in technicians. According to the unit, there are 2 people in the group department, 186 in daye peak, 89 in Yunnan peak, 56 in pharmaceutical company, 6 in international trade company and 41 in peak health. For employees who apply for qualifications above level 3, Group Barton organized a unified review. According to the final results, more than 6 per cent of the total number of persons rated as three or more qualified. (this newspaper reporter)
2020
07-31
Group Party Committee to determine the annual work plan
The party Committee of the group company has determined its work ideas and work plan for 2017 a few days ago, and relevant work has been arranged below. In view of the current new political and economic situation and the task of enterprise transformation and development, the general requirements of the Party Committee of the Group Company for 2017 are: to thoroughly study and implement the spirit of the Sixth Plenary Session of the 18th CPC Central Committee and the series of important speeches by General Secretary Xi Jinping, the spirit of the Seventh Party Congress of Jinhua City, to closely revolve around the center of enterprise production, operation and reform and development, and to adhere to scientific development and cross-regional development as the first priority, in order to continue to carry out the study and education of "five stars striving for innovation" and "two learning and one doing", we should highlight the main line of comprehensively and strictly administering the party according to the rules, firmly establish the political awareness, overall situation awareness, core awareness and alignment consciousness of the majority of Party members and cadres, strengthen and improve the party building work in enterprises in the spirit of reform, and strive to improve the scientific, standardized and institutionalized level of Party building work in enterprises, in order to promote the scientific development of the group company, leapfrog development and harmonious development, it provides a strong political, ideological and organizational guarantee. The working idea of the Party Committee of the Group Company in 2017 is to focus on "one center", adhere to "one concept", highlight "three key points" and do a good job in "three constructions". That is: centering on the "one center" of enterprise production, operation and reform and development, we should strive to strengthen the "one concept" of "the organic unity of the party's leadership and the improvement of corporate governance"; to "thoroughly implement the main responsibility of the party committee; continue to carry out the study and education of" two learning and one doing "; and improve the system of party building work" as the "three key points", and focus on "team building and team building
2020
07-31
Yunnan peak through the safety standard secondary acceptance
On March 21, Yunnan Jianfeng Cement Company successfully passed the evaluation and acceptance of secondary enterprises for safety production standardization. On the same day, a review team composed of leaders of the Yunnan Provincial Work Safety Supervision Bureau and relevant experts reviewed the implementation of the establishment of Yunnan Jianfeng safety production standardization secondary enterprises. According to the 13 elements involved in the "Standard for Assessment and Rating of Safety Production Standardization in Cement Enterprises", the review team conducted strict assessment and scoring item by item through grouping to check the site and review the data, and finally determined that Yunnan Peak passed the standard acceptance of safety standardization secondary enterprises. Yunnan Jianfeng has always attached great importance to safety production. After passing the three-level safety standard enterprise review in 2015, in order to raise the level of enterprise safety management to a new level, in 2016, it began to create secondary safety standardization. Over the past year, Yunnan Jianfeng has insisted on taking the creation of secondary safety standards as the top priority of production and operation management, and has formulated an implementation plan for production safety standardization in accordance with the requirements of national standardization norms. the content covers production safety responsibility system, education and training, safety inspection, safety facilities management and other safety production management standards, systems and post safety operation procedures, while further strengthening daily safety inspection and regularly organizing emergency plan drills, strengthen the investigation and rectification of potential safety hazards and the supervision of important hazard sources, and further consolidate the foundation of enterprise safety production management. After the review, Zhou Jiping, general manager of Yunnan Jianfeng, said that Yunnan Jianfeng will take this standard as a new starting point. On the basis of consolidating the accident-free achievements in production safety for two consecutive years, it will conscientiously implement the main responsibility of production safety and cultivate
2020
07-31
Yunnan peak through the safety standard secondary acceptance
On March 21, Yunnan Jianfeng Cement Company successfully passed the evaluation and acceptance of secondary enterprises for safety production standardization. On the same day, a review team composed of leaders of the Yunnan Provincial Work Safety Supervision Bureau and relevant experts reviewed the implementation of the establishment of Yunnan Jianfeng safety production standardization secondary enterprises. According to the 13 elements involved in the "Standard for Assessment and Rating of Safety Production Standardization in Cement Enterprises", the review team conducted strict assessment and scoring item by item through grouping to check the site and review the data, and finally determined that Yunnan Peak passed the standard acceptance of safety standardization secondary enterprises. Yunnan Jianfeng has always attached great importance to safety production. After passing the three-level safety standard enterprise review in 2015, in order to raise the level of enterprise safety management to a new level, in 2016, it began to create secondary safety standardization. Over the past year, Yunnan Jianfeng has insisted on taking the creation of secondary safety standards as the top priority of production and operation management, and has formulated an implementation plan for production safety standardization in accordance with the requirements of national standardization norms. the content covers production safety responsibility system, education and training, safety inspection, safety facilities management and other safety production management standards, systems and post safety operation procedures, while further strengthening daily safety inspection and regularly organizing emergency plan drills, strengthen the investigation and rectification of potential safety hazards and the supervision of important hazard sources, and further consolidate the foundation of enterprise safety production management. After the review, Zhou Jiping, general manager of Yunnan Jianfeng, said that Yunnan Jianfeng will take this standard as a new starting point. On the basis of consolidating the accident-free achievements in production safety for two consecutive years, it will conscientiously implement the main responsibility of production safety and cultivate
2020
07-31