Yunnan peak rainy season maintenance busy
Release time:
2020-08-14
Major Project Special Person Responsible for Mechanized Operation Efficiency
Yunnan Peak Rainy Season Maintenance Busy
News With the advent of the rainy season, Yunnan is gradually entering the off-season of cement sales. Yunnan Peak Cement Company seizes this opportunity to overhaul the production line. 8 24 , following the maintenance of the cement mill grinding system, the planned maintenance of the kiln system for 15 days was also started.
kiln system is an important part of cement production line, and its operation quality is directly related to whether the production can be carried out normally and the quality of cement products. In order to further eliminate the potential safety hazards of the equipment and improve the effective operation rate of the kiln system, combined with the actual conditions of the equipment operation cycle and safety and environmental protection management, Yunnan Jianfeng organized this overhaul according to the principle of "safety first, quality first, and progress controlled, the main contents include replacement of some tertiary air ducts, technical renovation of clinker inclined zippers, replacement of raw mill hydraulic system and conveying chute, replacement of kiln supporting wheel, replacement of blades of coal vertical mill separator, maintenance of limestone crusher, replacement of refractory materials in kiln, etc.
Due to the large number of maintenance projects, heavy tasks and many cross-operation points, in order to ensure the smooth completion of the work, Yunnan Jianfeng reasonably formulated the maintenance plan, with General Manager Zhou Jiping as the maintenance commander, fully responsible for the development of various tasks during the maintenance period, unified arrangement and deployment of maintenance forces, and strictly in accordance with the principle of "six implementation" of maintenance, the production and manufacturing department carefully sorted out the spare parts and maintenance tools needed for the maintenance in advance, the purchasing department will purchase large materials such as refractory bricks, castable, kiln supporting wheel, clinker inclined zipper technical transformation equipment in place on time. Before the kiln was shut down, Yunnan Jianfeng also called on the main repair personnel and outsourcing construction teams to verify one by one for the preparation and schedule arrangement of the maintenance, so as to ensure the normal development of the work.
Compared with previous maintenance, this maintenance has implemented a special person responsibility system for major maintenance projects, clarifying the key points of maintenance management for process, machinery and electrical specialties. Each major maintenance project has designated a special person to track, strengthen the quality acceptance of maintenance projects, prevent maintenance rework, and ensure good maintenance process control. The maintenance coordination meeting will be held on time at 4 : 30 every afternoon to make unified coordination arrangement and arrangement and strengthen communication and coordination among various operation points. During the maintenance, it was also the first time to try to carry out mechanized operations of firebrick demolition and cleaning, which effectively improved the construction efficiency.
In view of the safety management during the maintenance period, Yunnan Peak has not only confirmed the safety of internal and external personnel involved in the maintenance in advance, but also set up a special safety inspection team to be responsible for the safety inspection of sub-regional and sub-projects on the maintenance site, strictly investigate the "three violations" and other behaviors on the site, strengthen the safety supervision on the maintenance site, and strictly implement the safety inspection rules and regulations, educate employees to consciously abide by safe operation procedures, civilized construction and standardized operation, and enhance the safety and autonomy awareness of maintenance personnel; Strengthen supervision and control from the aspects of safety knowledge publicity, power cut-off, hazardous operation approval, cross-operation and outsourcing maintenance safety to ensure the smooth progress of maintenance work.
Yunnan Jianfeng Comprehensive Department has also done a good job in the maintenance logistics support service. It not only sets up maintenance service stations on site, provides hot tea, bottled mineral water, etc., but also organizes personnel from logistics functional departments to participate in voluntary labor on site, providing strong logistics support for the inspectors.
At present, the maintenance work of Yunnan Jianfeng kiln system is progressing in an orderly manner, and the maintenance site is in good order. All maintenance teams are actively seizing time and progress, striving to complete the maintenance tasks with good quality and quantity as planned, so as to prepare for the normal development of production afterwards. (Liu Fengbin Song Xiaofei Ma Xufeng)
More information
Editor's note: During the National Day, the "Jinhua New Observation" column of Jinhua TV Station launched a series of reports on "National Day New Observation: New Development of Old Enterprises" to understand the new developments of those old enterprises that have grown up with New China in the new era. October 3 broadcast of the "peak of the 'centennial 'ideal", about the development of the peak group and the future direction of development. The "century" ideal of the peak Jinhua TV reporter Wang Dujuan Jiang Qian host: speaking of Zhejiang Jianfeng Group Co., Ltd., Jinhua people are no stranger. The older generation of Jinhua people are more familiar with, may be the predecessor of Jianfeng Group-Jinhua Cement Factory. Open the first old photo 58 years ago, surrounded by mountains and a rice field in the middle. Old Jinhua can see at a glance that this is the Wise Temple, 8 kilometers north of Jinhua City and east of the former Zhuangtou of Luodian Town. In August 1958, the first group of pioneers came here and built Jinhua's first cement factory on a desolate hillside of 16.94 mu with a pair of hands and warm blood. From the earliest cattle-drawn ball forming machine to the electric ball forming machine, from pure manual labor to machine substitution, it took 26 years of hard work. By 1983, the annual output of peak cement reached 120000 tons, the output value was 6.75 million yuan, and the profit was 2.4 million yuan. In these 26 years, the cement plant has experienced a difficult period of the country, and the ten-year catastrophe of the "Cultural Revolution" has finally ushered in a good time of reform and opening up with tenacious vitality, laying the foundation for steady development in the future. Looking at these old pictures,
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Jianfeng won the Zhejiang Industrial Award
A few days ago, we learned from the relevant departments of Zhejiang Province that the company won the 2016 "Zhejiang Industrial Award Silver Award". Zhejiang Industrial Award was established in 2014 and is selected every two years. The purpose of carrying out the selection and commendation of the Zhejiang Industrial Awards is to thoroughly implement the "August 8 Strategy", comprehensively implement the innovation-driven development strategy, speed up the industrial transformation and upgrading with the "four for three" as the starting point, and commend the adherence to the scientific concept of development. adhere to industry, conscientiously fulfill social responsibilities, establish a modern enterprise system, and take a new road of industrialization with characteristics. The evaluation work is jointly organized and implemented by Zhejiang Industrial Economic Federation, Enterprise Federation, Entrepreneur Association, relevant provincial industry associations, municipal industrial economic federations, enterprise federations, entrepreneur associations, and relevant units. The award review committee is composed of relevant government departments, provincial "three committees", relevant provincial industry associations, and experts in industrial economy, management, finance, taxation, quality, environmental protection, safety, technology, and law, the participating enterprises are comprehensively evaluated from the aspects of industry demonstration role, scientific and technological innovation, economic benefits, resource utilization, environmental protection, brand strategy, product quality, production safety, social responsibility, enterprise management, human resources and so on. "The enterprises that have won the Zhejiang Industrial Award this time are all outstanding enterprises that have made significant contributions to the promotion of Zhejiang's economic development; they are all leading enterprises, backbone enterprises, and high-growth enterprises from different industries, representing the scale of Zhejiang's industrial development. The direction and leading spirit represent the highest level of Zhejiang's industrial development." According to the organizers related negative
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-31
Peak Cement Successfully Enters Lancang Airport Project
News from our newspaper On September 26, the first batch of airport runway cement produced by Yunnan Jianfeng Cement Company was successfully delivered to the Lancang Airport site, which marked another important step in the expansion of Jianfeng Cement in the southwest Yunnan market. Lancang Airport is located in Donghi Town, Lancang Lahu Autonomous County, Pu'er City. It is the center of the "three counties" and "Pu'er Green Triangle" tourist areas of Lancang, Menglian and Ximeng, with a wide range of radiation and obvious location advantages. The project is a national "Twelfth Five-Year Plan" construction project and a key construction project in Yunnan Province. It was approved by the State Council and the Central Military Commission in January 2013. It started construction at the end of November 2014 and is expected to be completed in April 2017. The current project of Lancang Airport is designed to meet the target of 250000 passenger throughput and 750 tons of cargo throughput by 2020, including the construction of a 2600-meter-long and 45-meter-wide runway, the construction of a new 3000-square-meter terminal building and 4 apron parking spaces, including communication, navigation, lighting, meteorology and other supporting projects. The total investment of the project is 1.533 billion yuan. Upon completion, it can be used for Boeing 737 series, Airbus A319 and A320 series, MA-60 and other passenger aircraft take off and land. Since the start of the Lancang Airport project, Yunnan Peak has listed it as an important goal to strive. Compared with ordinary cement, special cement for airport runways has the characteristics of small shrinkage, strong wear resistance, good frost resistance and low alkali content in addition to the requirements of ordinary 42.5 Portland cement. To this end, Yunnan peak in the project to strive for at the same time, the collection of technical forces to tackle the problem, in the clinker composition to determine, cooked.
2020
07-30
Peak two enterprises were commended
On September 23, the launching ceremony of the 2016 Jinhua Zhejiang Shopping Festival and the 2015 Jinhua Honest Enterprise Commendation Conference were held in the urban people's square. Jianfeng Group's Jinhua Jianfeng Pharmacy Chain Co., Ltd. and Zhejiang Jianfeng International Trade Co., Ltd. were commended.
2020
07-31