2020-08-14
Yunnan peak 110kV total reduction transformer T wiring reconstruction completed
news # November 26 , 27 , after intense construction, yunnan Jianfeng Cement Company successfully realized the conversion of 110kV total reduction from the original T to 110kV Mu (Mummy River) Ping (Da Ping Zhang) line to 110kV Mu Lan Line T , and officially started power transmission, which not only solved the worries of production power consumption, but also reduced the line rental fee and saved the cost. At the initial stage of
project construction, in order to solve the power consumption problem, under the coordination of Pu'er municipal government, Yunnan power grid company determined that "the initial new cement plant total reduction transformer T is connected to mummy river-dapingzhang (user asset) 110kV line as the transition scheme, after the completion of 110kV six-shun transformer, the power supply scheme of the new 1 back to 110kV line connected to 110kV 6 smooth transformer" for the total substation of the cement plant. Due to the slow load growth in the power supply area of Liushun Town, the power supply point 110kV Liushun of Yunnan Peak Permanent Power Supply Scheme will not start construction during the 13th Five-Year Plan period. On the one hand, the existing transition scheme restricts the long-term development of Yunnan Peak, on the other hand, it restricts the power demand of Yunnan Shanshui Copper Company Phase II Project, and at the same time, it needs to pay line rental fee every year, greatly increasing the operating cost.
In order to completely solve the worries of electricity consumption, Yunnan Jianfeng applied to Pu 'er Power Supply Bureau on 2015 1 15 to change the original power supply scheme to reduce the operating cost of the enterprise, improve the reliability of power supply and meet the future demand for electricity consumption growth. After coordination by provincial and municipal power departments, Yunnan power grid company agreed to adjust the power supply scheme of Yunnan peak total reduction and transformation in 2016 , and changed the original T to 110kV mummy river-dapingzhang line to T to 110KV mulan line. After the completion of 2017 220kV Lancang Tangsheng transformer, it will be disconnected from the tower of 110kV Mulan line 54 , which will be the special power supply line for Yunnan peak. After received the approval of the provincial network company, Yunnan peak immediately organized a series of work such as exploration, design, land occupation compensation, construction, etc. After careful deployment, the line
connection conversion was successfully realized on and 27 as planned, ensuring the long-term stable power consumption of Yunnan peak, at the same time, the line rental fee of 250 yuan can be reduced every year. (Tan Guojian Shi Wen Ting)
More information
The company's vocational skill level independently identifies two new occupations
A few days ago, after the examination and approval of the Jinhua Municipal Bureau of Human Resources and Social Security, and reported to the Provincial Department of Human Resources and Social Security for examination and filing, Jianfeng Group's independent identification level of vocational skills was based on last year. Two new occupations (types of work) are chemical inspectors and organic synthesis workers.
2022
05-20
On May 12, Cai Xiaochun, deputy secretary of the Party group of Zhejiang Federation of industry and commerce, and his party visited Jianfeng group for investigation, visited Jinxi factory area of Jianfeng pharmaceutical factory and Jinxi internationalization project site, and had a discussion with Jiang Xiaomeng, chairman of the group company, Huang Jinlong, deputy general manager of the group company and general manager of the pharmaceutical company.
2022
05-20
On the afternoon of April 6, Jiang Xiaomeng, chairman of the group company, was invited to participate in the Jinhua News Client Financial Media Interview column "Night Talk of the Two Sessions", as a representative of the Jinhua Municipal People's Congress, to talk about suggestions for the future development of Jinhua enterprises. As the chairman of the Jinhua City Federation of Industry and Commerce, Jiang Xiaomeng has a personal experience of various problems encountered in the development of Jinhua enterprises. After careful investigation and full preparation, he put forward two proposals on strengthening the empowerment and allocation of production factors and further enhancing the market competitiveness of enterprises in our city and further promoting the compliance construction of private enterprises in our city and reducing the risk of enterprise operation. In the "two sessions night talk" interview, he put forward his own views on these two topics.
2022
04-12
Group Companies Commend 2021 Advanced
On the morning of January 26, the group company held the 2021 annual summary commendation meeting to review the work of the previous year, make arrangements for the work of 2022, sign the 2022 economic responsibility system with various professional companies and directly affiliated enterprises, and solemnly commend the 2021 advanced collectives and individuals.
2022
02-08
Group Company Convenes Workers' Representative and Trade Union Member Representative Conference
The group company held a representative meeting of staff representatives and trade union members, elected members of the eighth trade union committee and members of various special committees, and Shi Fu was elected chairman of the eighth trade union of the group trade union.
2022
02-08
The group company held an annual safety and environmental protection work conference to comprehensively summarize and review the safety and environmental protection work in 2021, make arrangements for the safety and environmental protection work in 2022, and sign the safety and environmental protection work responsibility system.
2022
02-08