Completion of Reconstruction of 110kV T Connection Line of Yunnan Peak
Release time:
2020-08-14
Yunnan peak 110kV total reduction transformer T wiring reconstruction completed
news # November 26 , 27 , after intense construction, yunnan Jianfeng Cement Company successfully realized the conversion of 110kV total reduction from the original T to 110kV Mu (Mummy River) Ping (Da Ping Zhang) line to 110kV Mu Lan Line T , and officially started power transmission, which not only solved the worries of production power consumption, but also reduced the line rental fee and saved the cost. At the initial stage of
project construction, in order to solve the power consumption problem, under the coordination of Pu'er municipal government, Yunnan power grid company determined that "the initial new cement plant total reduction transformer T is connected to mummy river-dapingzhang (user asset) 110kV line as the transition scheme, after the completion of 110kV six-shun transformer, the power supply scheme of the new 1 back to 110kV line connected to 110kV 6 smooth transformer" for the total substation of the cement plant. Due to the slow load growth in the power supply area of Liushun Town, the power supply point 110kV Liushun of Yunnan Peak Permanent Power Supply Scheme will not start construction during the 13th Five-Year Plan period. On the one hand, the existing transition scheme restricts the long-term development of Yunnan Peak, on the other hand, it restricts the power demand of Yunnan Shanshui Copper Company Phase II Project, and at the same time, it needs to pay line rental fee every year, greatly increasing the operating cost.
In order to completely solve the worries of electricity consumption, Yunnan Jianfeng applied to Pu 'er Power Supply Bureau on 2015 1 15 to change the original power supply scheme to reduce the operating cost of the enterprise, improve the reliability of power supply and meet the future demand for electricity consumption growth. After coordination by provincial and municipal power departments, Yunnan power grid company agreed to adjust the power supply scheme of Yunnan peak total reduction and transformation in 2016 , and changed the original T to 110kV mummy river-dapingzhang line to T to 110KV mulan line. After the completion of 2017 220kV Lancang Tangsheng transformer, it will be disconnected from the tower of 110kV Mulan line 54 , which will be the special power supply line for Yunnan peak. After received the approval of the provincial network company, Yunnan peak immediately organized a series of work such as exploration, design, land occupation compensation, construction, etc. After careful deployment, the line
connection conversion was successfully realized on and 27 as planned, ensuring the long-term stable power consumption of Yunnan peak, at the same time, the line rental fee of 250 yuan can be reduced every year. (Tan Guojian Shi Wen Ting)
More information
The company organized "charity one day donation"
On the morning of October 22, in the lobby on the first floor of Jianfeng Building, all cadres and employees of the group headquarters and subordinate enterprises working in Jianfeng Building participated in the 2021 "Charity Day Donation" activity to offer their love to Jinhua charity. In the next few days, the company's subordinate enterprises also organized "charity one-day donation" activities one after another.
2021
11-01
The company organizes new employee induction training
"Growth is more important than success. I hope everyone can become the backbone and pillars of the peak as soon as possible." On September 2, Yu Jianhong, general manager of the group company, put forward ardent hopes in the face of new employees. On the 2nd and 3rd, the group company organized induction training for new employees recruited in the past year. The group company chairman Jiang Xiaomeng, general manager Yu Jianhong and other leaders and relevant department heads gave lectures to them.
2021
09-13
Daye Peak: Typical Regional Industrial Green Development
On August 23, Huangshi Radio and Television Station broadcast the special program of "Strengthening Overall Planning and Promoting Energy Saving and Emission Reduction in Industrial Field". Daye Jianfeng Cement Company, as a typical enterprise with outstanding achievements in establishing green factories and energy saving and emission reduction in Huangshi area, appeared in the program.
2021
09-01
Yunnan Peak Helps Border Epidemic Prevention and Control
On August 22, Yunnan Peak Cement Company, through the Red Cross Society of Pu'er City and the Epidemic Prevention Headquarters of Pu'er City, donated vacuum insulation pots with a total value of 800000 yuan to the four border counties for the prevention and control of the new coronary pneumonia epidemic in the border area, and supported the prevention and control of the epidemic at the border with practical actions.
2021
09-01
Group Party Committee to Learn "July 1" Important Speech
On August 13, the party committee of the group company held a special meeting to collectively study General Secretary Xi Jinping's important speech at the celebration meeting of the 100 anniversary of the founding of the Communist Party of China, convey the requirements of the party committee at a higher level, and make arrangements for organizing party members of the company to study the "July 1" speech.
2021
08-23
Spike Ranked 2020 China's Top 100 Cement Clinker Production Capacity
Recently, the company received the "2020 China Cement Clinker Production Capacity Top 100" plaque issued by China Cement Network. The ranking of China's top 100 cement clinker production capacity is organized and evaluated by China Cement Network, an authoritative information platform for the domestic cement industry. It is released according to the actual clinker production capacity of each cement enterprise at the end of last year. The company has been ranked in the top 100 list for many consecutive years.
2021
08-23