Temporary Electricity Safety Common Sense
Temporary electricity refers to the design, installation, use, maintenance and removal of low-voltage power systems using electric equipment and lighting on the production and construction sites during temporary overhaul or maintenance and engineering construction. The main facilities and materials for temporary power utilization include transformers, power distribution cabinets, distribution boxes, switch boxes, cables, wires, electrical tools, electric tools, lighting fixtures, electrical equipment, etc. Basic management requirements for
temporary power consumption:
1.
temporary power consumption organization design shall be prepared for the construction site with 5or more temporary power consumption equipment or the total capacity of equipment is 50kW or more. 2.
Temporary electricity consumption organization design must follow the "preparation, review and approval " procedure, which shall be organized and compiled by electrical engineering technicians and implemented after being reviewed by relevant departments and approved by the technical director of the enterprise with legal personality. 3.
Temporary power consumption project shall be constructed according to the design drawing, and shall be jointly accepted by relevant units before being put into use after being qualified.4.
Temporary electricity use must establish safety technical files, which shall be established and managed by electrical technicians. Among them, "electrician installation, inspection, maintenance and demolition work record " can be assigned to be managed by an electrician, which shall be reviewed and approved by the main person in charge or project manager every week, and shall be filed uniformly after the temporary power consumption project is demolished. 5.
Temporary power consumption shall be checked regularly, potential safety hazards shall be handled in time, and rechecked and accepted.Basic requirements for electricians and electricity users:
1.
Electricians must pass the examination and obtain the special operation certificate before taking up their posts; Other electricity users must undergo safety training and technical disclosure before they can take up their posts.2.
Installation, inspection, maintenance or removal of temporary electrical equipment and lines must be completed by an electrician and supervised by a special person.All kinds of electricity users should master the basic knowledge of safe electricity use and the performance of the equipment used, and should meet the following regulations:
1.
Before using electrical equipment, they must wear and equip corresponding labor protection articles according to regulations, and check electrical devices and protection facilities. It is strictly forbidden for equipment to operate with diseases.2.
Keep and maintain the equipment used, report and solve any problems found in time;3.
The switch box of temporarily deactivated equipment must disconnect the power isolation switch and close the door and lock it.4.
When moving electrical equipment, the power supply must be cut off by an electrician and properly handled. Introduction toElectrical Equipment:
1.
Electrical Equipment Switches shall adopt automatic control electrical appliances such as contactors and relays, and manual two-way transfer switches shall not be used as control electrical appliances.2. In the switch box of Class I
and Class IImetal shell hand-held electric tools, the rated leakage action current of the leakage protector shall not be greater than 15mA , and the rated leakage action time shall not be greater than 0.1s . 3.
When operating in wet places and on metal frames, Class IIor Class III hand-held power tools powered by safety isolation transformers must be selected. 4.
It is strictly forbidden to use Class Ihand-held electric tools in wet places or on metal frames. 5.
The load line of the water pump must adopt waterproof rubber sheathed copper core flexible cable. Any damage and joints are strictly prohibited, and no external force is allowed.When cleaning, inspecting and maintaining concrete mixers, steel bar processing machinery, woodworking machinery and other equipment, the switch box must first be switched off and powered off, showing visible power breaking points, and the door must be closed and locked.
hang the sign of no closing and be monitored by special personnel. (Liu Fengbin)
More information
Peak re-listed China's top 100 cement production capacity Daye peak won the "smart factory leader"
On July 11-12, the 2022 China Cement Industry Summit and TOP100 Award Ceremony organized by China Cement Network, an authoritative media of China's cement industry, was held in Hangzhou. Jianfeng Group once again ranked among the top 100 cement clinker production capacity in China.
2022
08-04
On the afternoon of July 12, the party Committee of the group company held a special meeting attended by party Committee members, senior and middle-level management backbones, heads of grass-roots party organizations and all party members of the group headquarters to learn and convey the spirit of the 15th party congress of the communist party of China in Zhejiang province.
2022
07-24
On the morning of July 1, more than 40 members of the group's party committee, party members of various branches of the group headquarters, and party members of subordinate enterprise branches went to the Shuanglong Hydropower Station, the Red Education Base of Jinhua City, to receive party spirit and revolutionary tradition education.
2022
07-14
Vocational skill level identification examination!
On June 16 and 18, the theoretical and practical examinations for the determination of professional skill level in the peak pharmaceutical sector were held successively in Jinxi pharmaceutical factory. The independent identification of vocational skill level includes three occupations (types of work): pharmaceutical preparation worker, chemical inspector and organic synthesis worker, basically covering the main posts in the pharmaceutical sector, with a total of 125 employees signing up for the identification.
2022
06-21
On June 16, the Jianfeng Pharmaceutical Quality Research and Development Party Branch and the Jinhua Vocational Skills Management Service Center Party Branch held a signing ceremony in Jinxi Factory to establish a party building alliance.
2022
06-21
Jinhua Mayor Xing Zhihong to Peak Research
On the afternoon of June 1, Jinhua Mayor Xing Zhihong, Wucheng District Party Committee Secretary Gao Feng, District Mayor Hu Yuxian, and heads of the Municipal Economic and Information Bureau, Development and Reform Bureau and other departments went to the group headquarters to discuss and exchange with the leaders of the group company to understand the development of the enterprise. Solicit opinions and suggestions from enterprises on government work. After understanding the current business situation of the peak, Xing Zhihong pointed out that focus, follow the right path, frontier, steady, is the peak to long-term prosperity of the magic weapon, must continue to adhere.
2022
06-13