Common sense of temporary electricity safety
Release time:
2020-08-17
Temporary Electricity Safety Common Sense
Temporary electricity refers to the design, installation, use, maintenance and removal of low-voltage power systems using electric equipment and lighting on the production and construction sites during temporary overhaul or maintenance and engineering construction. The main facilities and materials for temporary power utilization include transformers, power distribution cabinets, distribution boxes, switch boxes, cables, wires, electrical tools, electric tools, lighting fixtures, electrical equipment, etc. Basic management requirements for
temporary power consumption:
1.
temporary power consumption organization design shall be prepared for the construction site with 5or more temporary power consumption equipment or the total capacity of equipment is 50kW or more. 2.
Temporary electricity consumption organization design must follow the "preparation, review and approval " procedure, which shall be organized and compiled by electrical engineering technicians and implemented after being reviewed by relevant departments and approved by the technical director of the enterprise with legal personality. 3.
Temporary power consumption project shall be constructed according to the design drawing, and shall be jointly accepted by relevant units before being put into use after being qualified.4.
Temporary electricity use must establish safety technical files, which shall be established and managed by electrical technicians. Among them, "electrician installation, inspection, maintenance and demolition work record " can be assigned to be managed by an electrician, which shall be reviewed and approved by the main person in charge or project manager every week, and shall be filed uniformly after the temporary power consumption project is demolished. 5.
Temporary power consumption shall be checked regularly, potential safety hazards shall be handled in time, and rechecked and accepted.Basic requirements for electricians and electricity users:
1.
Electricians must pass the examination and obtain the special operation certificate before taking up their posts; Other electricity users must undergo safety training and technical disclosure before they can take up their posts.2.
Installation, inspection, maintenance or removal of temporary electrical equipment and lines must be completed by an electrician and supervised by a special person.All kinds of electricity users should master the basic knowledge of safe electricity use and the performance of the equipment used, and should meet the following regulations:
1.
Before using electrical equipment, they must wear and equip corresponding labor protection articles according to regulations, and check electrical devices and protection facilities. It is strictly forbidden for equipment to operate with diseases.2.
Keep and maintain the equipment used, report and solve any problems found in time;3.
The switch box of temporarily deactivated equipment must disconnect the power isolation switch and close the door and lock it.4.
When moving electrical equipment, the power supply must be cut off by an electrician and properly handled. Introduction toElectrical Equipment:
1.
Electrical Equipment Switches shall adopt automatic control electrical appliances such as contactors and relays, and manual two-way transfer switches shall not be used as control electrical appliances.2. In the switch box of Class I
and Class IImetal shell hand-held electric tools, the rated leakage action current of the leakage protector shall not be greater than 15mA , and the rated leakage action time shall not be greater than 0.1s . 3.
When operating in wet places and on metal frames, Class IIor Class III hand-held power tools powered by safety isolation transformers must be selected. 4.
It is strictly forbidden to use Class Ihand-held electric tools in wet places or on metal frames. 5.
The load line of the water pump must adopt waterproof rubber sheathed copper core flexible cable. Any damage and joints are strictly prohibited, and no external force is allowed.When cleaning, inspecting and maintaining concrete mixers, steel bar processing machinery, woodworking machinery and other equipment, the switch box must first be switched off and powered off, showing visible power breaking points, and the door must be closed and locked.
hang the sign of no closing and be monitored by special personnel. (Liu Fengbin)
More information
Representatives of the 20th Congress preached the 20th Congress at the peak.
On the afternoon of November 11, a special lecture on the spirit of the Party's 20th Congress was held in the conference room of the Peak Building. Yang Xiayun, a representative of the 20th National Congress, walked into the peak and preached his understanding of the spirit of the 20th National Congress for Party members through personal experience.
2022
11-23
The group party committee organizes and learns the twenty spirits.
On the afternoon of October 28, the party Committee of the group organized all members to hold a special study meeting to earnestly study and understand the communique of the first plenary session of the 20th central Committee of the communist party of China and the revision of the party constitution. Jiang Xiaomeng, Secretary of the Party committee of the group, stressed at the study meeting that the 20th National Congress of the Communist Party of China has drawn a grand blueprint for building a socialist modern country in an all-round way, opened a new chapter in the era of national development, and pointed out the direction for the future development of enterprises. Party organizations at all levels of the group should pay full attention to and earnestly implement it, actively organize party members and cadres to learn the spirit of the spirit of the 20th National Congress, And to guide the future work practice.
2022
11-01
Spike Party Members and Cadres Watch the Opening Meeting of the 20th Congress
At 10 a.m. on October 16, the 20th National Congress of the Communist Party of China was solemnly opened in the Great Hall of the People in Beijing. Xi Jinping delivered a report to the Party's 20th National Congress on behalf of the 19th Central Committee. The group company attaches great importance to and carefully deploys, and organizes all party members and management backbones of the group headquarters and subsidiaries to watch the live broadcast of the opening meeting through the Internet, TV and other methods.
2022
10-23
Jiang Xiaomeng was hired as the "Shuanglong Escort" entrepreneurial mentor.
On September 16, Jiang Xiaomeng, Secretary of the Party committee and chairman of the group company, was employed as the entrepreneurial mentor of "Shuanglong escort" at the launching ceremony of the special action of "Shuanglong escort steady progress and quality improvement" held in Jinhua City and the promotion meeting of innovative products of key talent enterprises in Jinhua City.
2022
09-27
From August 18th to 19th, the 12th Congress of the Zhejiang Federation of Industry and Commerce was held in Hangzhou, and the 12th leadership of the Provincial Federation of Industry and Commerce was elected. Jiang Xiaomeng, Secretary of the Party Committee and Chairman of the Group, was re-elected as Vice President of Zhejiang Chamber of Commerce.
2022
09-01