2018 10# July 18 Early in the morning, I received a phone call from manager Zhou of the quality department of a major customer company, saying that the HYA53 cable produced by our company was sent to a well-known testing organization in Shanghai for testing, and many indicators of the product failed. Hearing the news, I was like a thunderbolt. For so many years, there has never been a third-party failure test for local telephone cables. Is the quality of our products really so poor this time? If it is true, then where is the reputation of our company, where is the integrity, and will customers still exist?
After the tension, I immediately asked what indicator was unqualified. The customer then sent me the unqualified items. I quickly looked at them and found that among the nearly 20 indicators, there were four unqualified indicators: resistance, capacitance, attenuation and near string. I immediately went to check the production and inspection records, and also asked the employees in charge of production and inspection. The records showed that the product indexes were qualified and the indexes were relatively large, and there was no abnormal situation in the production process. Resistance, capacitance and attenuation are all related to length. I immediately realized that this sample may be a problem with the test length.
So I asked the relevant personnel if there was any length deviation. The operator reflected that because he knew that this cable was a sample for testing, more than 2 meters were reserved at the inner and outer ends for testing the length of the wiring, and the length was written as 100 meters according to the customer's requirements. Therefore, the actual length of the cable should be about 105 meters. I immediately contacted the personnel of the testing organization and asked her to help check whether there was any length deviation. The next day I got a reply, the actual length is 105-107 meters, and the testing organization tests according to 100 meters on the certificate. The
detection mechanism said that the resistance and capacitance indexes were qualified after conversion by length, but the attenuation and near string indexes were still unqualified after conversion by length. I wondered, not knowing how to explain, and asked for the cable to be retested, but was refused. So I asked the testing agency to send me the original data of the test. The testing agency did not agree with my request. They said that there was no practice of retesting unqualified products, and there was no precedent for sending the original data to customers.
The testing agency does not agree to retest. There are only two options before us: one is to re-produce a cable to test and help the customer get a qualified test report; The second is to analyze the test data of the product to see if the test is wrong. If there is a mistake, we can appeal. For our customers, there is no doubt that the first choice is the best. We can get the test report as soon as possible and have an explanation. It is undoubtedly very difficult for the testing organization to provide the original data. However, our general manager Li didn't think so after knowing the situation. He said that if we send the products for inspection again, the inspection fee of more than 10,000 yuan is a trivial matter. The key is that customers will think that we are not qualified even in the sample line, so the products we supply them must be junk products at ordinary times. We will be regarded as dishonest suppliers, and problems may occur in future cooperation, losing our most important customer right now. Therefore, we must confirm whether our products are really problematic. It is a very important step for testing agencies to provide data. If handled well, it may turn bad things into good things.
was deadlocked for nearly two weeks. The customer was eager to use the test report and asked us to get the qualified report as soon as possible, and some doubts were revealed in the words. The production department rearranged the production of a sample line. The sales department contacted the major customers in Jiangsu and borrowed their authoritative US DCM equipment for testing. The comprehensive management department arranged a special car and I personally sent the products to Jiangsu for testing. One day a back and forth, in exchange for satisfactory full performance qualified test results, which makes us more confident in our products. Using this convincing data, and under the strong request of our customers, the testing organization finally sent us the original data. After getting the data, the relevant personnel of the company held a special meeting to analyze and study the data, and found that the testing organization applied the standard incorrectly and caused the wrong judgment. We wrote the relevant misunderstanding and sent it to the testing agency, and they finally approved our complaint and re-judged the product as qualified. After
, manager Zhou told me in wechat: "you are right. I believe in the quality of your products, because your leaders attach great importance to the quality of products, and your professional level is higher than that of the testing institutions!" I sent her a happy smile. An unexpected storm finally cleared the weather and turned a bad thing into a good thing. At this time, I found the sun is so warm and bright ...... (Lu Chaofang)
More information
Peak re-listed China's top 100 cement production capacity Daye peak won the "smart factory leader"
On July 11-12, the 2022 China Cement Industry Summit and TOP100 Award Ceremony organized by China Cement Network, an authoritative media of China's cement industry, was held in Hangzhou. Jianfeng Group once again ranked among the top 100 cement clinker production capacity in China.
2022
08-04
On the afternoon of July 12, the party Committee of the group company held a special meeting attended by party Committee members, senior and middle-level management backbones, heads of grass-roots party organizations and all party members of the group headquarters to learn and convey the spirit of the 15th party congress of the communist party of China in Zhejiang province.
2022
07-24
On the morning of July 1, more than 40 members of the group's party committee, party members of various branches of the group headquarters, and party members of subordinate enterprise branches went to the Shuanglong Hydropower Station, the Red Education Base of Jinhua City, to receive party spirit and revolutionary tradition education.
2022
07-14
Vocational skill level identification examination!
On June 16 and 18, the theoretical and practical examinations for the determination of professional skill level in the peak pharmaceutical sector were held successively in Jinxi pharmaceutical factory. The independent identification of vocational skill level includes three occupations (types of work): pharmaceutical preparation worker, chemical inspector and organic synthesis worker, basically covering the main posts in the pharmaceutical sector, with a total of 125 employees signing up for the identification.
2022
06-21
On June 16, the Jianfeng Pharmaceutical Quality Research and Development Party Branch and the Jinhua Vocational Skills Management Service Center Party Branch held a signing ceremony in Jinxi Factory to establish a party building alliance.
2022
06-21
Jinhua Mayor Xing Zhihong to Peak Research
On the afternoon of June 1, Jinhua Mayor Xing Zhihong, Wucheng District Party Committee Secretary Gao Feng, District Mayor Hu Yuxian, and heads of the Municipal Economic and Information Bureau, Development and Reform Bureau and other departments went to the group headquarters to discuss and exchange with the leaders of the group company to understand the development of the enterprise. Solicit opinions and suggestions from enterprises on government work. After understanding the current business situation of the peak, Xing Zhihong pointed out that focus, follow the right path, frontier, steady, is the peak to long-term prosperity of the magic weapon, must continue to adhere.
2022
06-13