An unexpected "storm"
Release time:
2020-07-22
An unexpected "storm"
2018 10# July 18 Early in the morning, I received a phone call from manager Zhou of the quality department of a major customer company, saying that the HYA53 cable produced by our company was sent to a well-known testing organization in Shanghai for testing, and many indicators of the product failed. Hearing the news, I was like a thunderbolt. For so many years, there has never been a third-party failure test for local telephone cables. Is the quality of our products really so poor this time? If it is true, then where is the reputation of our company, where is the integrity, and will customers still exist?
After the tension, I immediately asked what indicator was unqualified. The customer then sent me the unqualified items. I quickly looked at them and found that among the nearly 20 indicators, there were four unqualified indicators: resistance, capacitance, attenuation and near string. I immediately went to check the production and inspection records, and also asked the employees in charge of production and inspection. The records showed that the product indexes were qualified and the indexes were relatively large, and there was no abnormal situation in the production process. Resistance, capacitance and attenuation are all related to length. I immediately realized that this sample may be a problem with the test length.
So I asked the relevant personnel if there was any length deviation. The operator reflected that because he knew that this cable was a sample for testing, more than 2 meters were reserved at the inner and outer ends for testing the length of the wiring, and the length was written as 100 meters according to the customer's requirements. Therefore, the actual length of the cable should be about 105 meters. I immediately contacted the personnel of the testing organization and asked her to help check whether there was any length deviation. The next day I got a reply, the actual length is 105-107 meters, and the testing organization tests according to 100 meters on the certificate. The
detection mechanism said that the resistance and capacitance indexes were qualified after conversion by length, but the attenuation and near string indexes were still unqualified after conversion by length. I wondered, not knowing how to explain, and asked for the cable to be retested, but was refused. So I asked the testing agency to send me the original data of the test. The testing agency did not agree with my request. They said that there was no practice of retesting unqualified products, and there was no precedent for sending the original data to customers.
The testing agency does not agree to retest. There are only two options before us: one is to re-produce a cable to test and help the customer get a qualified test report; The second is to analyze the test data of the product to see if the test is wrong. If there is a mistake, we can appeal. For our customers, there is no doubt that the first choice is the best. We can get the test report as soon as possible and have an explanation. It is undoubtedly very difficult for the testing organization to provide the original data. However, our general manager Li didn't think so after knowing the situation. He said that if we send the products for inspection again, the inspection fee of more than 10,000 yuan is a trivial matter. The key is that customers will think that we are not qualified even in the sample line, so the products we supply them must be junk products at ordinary times. We will be regarded as dishonest suppliers, and problems may occur in future cooperation, losing our most important customer right now. Therefore, we must confirm whether our products are really problematic. It is a very important step for testing agencies to provide data. If handled well, it may turn bad things into good things.
was deadlocked for nearly two weeks. The customer was eager to use the test report and asked us to get the qualified report as soon as possible, and some doubts were revealed in the words. The production department rearranged the production of a sample line. The sales department contacted the major customers in Jiangsu and borrowed their authoritative US DCM equipment for testing. The comprehensive management department arranged a special car and I personally sent the products to Jiangsu for testing. One day a back and forth, in exchange for satisfactory full performance qualified test results, which makes us more confident in our products. Using this convincing data, and under the strong request of our customers, the testing organization finally sent us the original data. After getting the data, the relevant personnel of the company held a special meeting to analyze and study the data, and found that the testing organization applied the standard incorrectly and caused the wrong judgment. We wrote the relevant misunderstanding and sent it to the testing agency, and they finally approved our complaint and re-judged the product as qualified. After
, manager Zhou told me in wechat: "you are right. I believe in the quality of your products, because your leaders attach great importance to the quality of products, and your professional level is higher than that of the testing institutions!" I sent her a happy smile. An unexpected storm finally cleared the weather and turned a bad thing into a good thing. At this time, I found the sun is so warm and bright ...... (Lu Chaofang)
More information
Daye Peak Launches Anti-"Three Violations" Special Activities
Recently, Daye Jianfeng Cement Company has set up a special leading group for "anti-three violations" activities headed by Zhang Fengliang, deputy general manager of the group company and general manager of Daye Jianfeng, to vigorously carry out anti-"three violations" activities throughout the plant. Most safety accidents come from illegal command, illegal operation and violation of labor discipline. In order to reduce or even put an end to the phenomenon of "three violations", eradicate persistent diseases in violation of rules and regulations, eliminate hidden dangers of accidents, standardize employees' production safety behavior, and prevent the occurrence of all kinds of production safety accidents, Daye Peak has carried out special activities against "three violations" according to the requirements of the implementation plan of "anti-three violations, accident prevention and safety protection" carried out by the Safety Committee of Baoan Town. The purpose is to strengthen employees' understanding of the harmfulness, make safety education and training more targeted, make the implementation of safety rules and regulations more in place, improve employees' awareness of safety production and safety skills, avoid personal injury accidents, misoperation accidents and other liability accidents caused by violations, and effectively achieve safety production standardization Anti-violation, procedural accident prevention, standardization to ensure safety, and fully achieve the 2016 safety production work goal. According to the plan, this activity is divided into three stages: the first stage is from September 1 to September 15, which is the mobilization and deployment stage; the second stage is from September 16 to October 15, which is the implementation stage; the third stage is from October 16 to October 20, which is the summary and improvement stage. The activities mainly carried out self-examination of "anti-three violations" by hanging safety slogans and banners, and organized the study of safety regulations such as "100 typical violations of production safety" and "post safety operation procedures".
2020
07-31
Daye Peak Launches Anti-"Three Violations" Special Activities
Recently, Daye Jianfeng Cement Company has set up a special leading group for "anti-three violations" activities headed by Zhang Fengliang, deputy general manager of the group company and general manager of Daye Jianfeng, to vigorously carry out anti-"three violations" activities throughout the plant. Most safety accidents come from illegal command, illegal operation and violation of labor discipline. In order to reduce or even put an end to the phenomenon of "three violations", eradicate persistent diseases in violation of rules and regulations, eliminate hidden dangers of accidents, standardize employees' production safety behavior, and prevent the occurrence of all kinds of production safety accidents, Daye Peak has carried out special activities against "three violations" according to the requirements of the implementation plan of "anti-three violations, accident prevention and safety protection" carried out by the Safety Committee of Baoan Town. The purpose is to strengthen employees' understanding of the harmfulness, make safety education and training more targeted, make the implementation of safety rules and regulations more in place, improve employees' awareness of safety production and safety skills, avoid personal injury accidents, misoperation accidents and other liability accidents caused by violations, and effectively achieve safety production standardization Anti-violation, procedural accident prevention, standardization to ensure safety, and fully achieve the 2016 safety production work goal. According to the plan, this activity is divided into three stages: the first stage is from September 1 to September 15, which is the mobilization and deployment stage; the second stage is from September 16 to October 15, which is the implementation stage; the third stage is from October 16 to October 20, which is the summary and improvement stage. The activities mainly carried out self-examination of "anti-three violations" by hanging safety slogans and banners, and organized the study of safety regulations such as "100 typical violations of production safety" and "post safety operation procedures".
2020
07-31
The water and soil conservation scheme of Daye Peak Mine passed the review.
The water and soil conservation plan of Jinshan limestone mine and Baiyunsi sand shale mine of Daye Peak Cement Company passed expert review a few days ago. In order to effectively prevent and control soil erosion, protect and rationally utilize water and soil resources, reduce water, drought, wind and sand disasters, and improve the ecological environment, in accordance with the "the People's Republic of China Soil and Water Conservation Law", "Management Measures for Soil and Water Conservation Programs for Development and Construction Projects" and other laws and regulations Relevant technical specifications and the requirements of local management departments, Daye Peak commissioned Daye City Soil and Water Conservation Test Station in May this year to prepare soil and water and soil and soil conservation plans for Jinshan limestone mine. Recently, the water and soil conservation plans of the two mines have been prepared and reviewed by experts. After nearly a day of careful review, the participating experts and leaders gave a high evaluation of the plan, and put forward some suggestions and opinions for improvement. At the same time, they fully affirmed Daye Peak's attitude of attaching great importance to the work of soil and water conservation in the mine, and unanimously agreed that the above two The plan passed the review. The service life of water and soil conservation scheme of Jinshan Limestone Mine and Baiyunsi Sand Shale Mine is 5 years. In the next five years, Daye Peak will entrust water and soil conservation supervision and monitoring, and gradually organize the implementation of prevention and control measures in accordance with the plan. By 2021, Daye Peak will prepare a technical evaluation report based on the implementation of the water and soil conservation plan, check the construction and implementation of responsibilities, evaluate the effect of soil erosion prevention and control, and apply for completion acceptance. (Daye Peak)
2020
07-31
Daye Peak Launches Anti-"Three Violations" Special Activities
Recently, Daye Jianfeng Cement Company has set up a special leading group for "anti-three violations" activities headed by Zhang Fengliang, deputy general manager of the group company and general manager of Daye Jianfeng, to vigorously carry out anti-"three violations" activities throughout the plant. Most safety accidents come from illegal command, illegal operation and violation of labor discipline. In order to reduce or even put an end to the phenomenon of "three violations", eradicate persistent diseases in violation of rules and regulations, eliminate hidden dangers of accidents, standardize employees' production safety behavior, and prevent the occurrence of all kinds of production safety accidents, Daye Peak has carried out special activities against "three violations" according to the requirements of the implementation plan of "anti-three violations, accident prevention and safety protection" carried out by the Safety Committee of Baoan Town. The purpose is to strengthen employees' understanding of the harmfulness, make safety education and training more targeted, make the implementation of safety rules and regulations more in place, improve employees' awareness of safety production and safety skills, avoid personal injury accidents, misoperation accidents and other liability accidents caused by violations, and effectively achieve safety production standardization Anti-violation, procedural accident prevention, standardization to ensure safety, and fully achieve the 2016 safety production work goal. According to the plan, this activity is divided into three stages: the first stage is from September 1 to September 15, which is the mobilization and deployment stage; the second stage is from September 16 to October 15, which is the implementation stage; the third stage is from October 16 to October 20, which is the summary and improvement stage. The activities mainly carried out self-examination of "anti-three violations" by hanging safety slogans and banners, and organized the study of safety regulations such as "100 typical violations of production safety" and "post safety operation procedures".
2020
07-30
Spike Pharmaceuticals Enters Infant Drug Market
Jindal Baby Drug Co., Ltd. Established Peak Pharmaceuticals to Enter Infant Drug Market Recently, Zhejiang Jindal Baby Drug Co., Ltd., a Sino-German joint venture controlled by Peak Pharmaceuticals, completed registration. Peak Pharmaceuticals will use this as a basis to introduce German technology and products and develop the infant drug market. Zhejiang Jindel Baby Drug Co., Ltd. was jointly funded by Jianfeng Pharmaceutical, Germany Gefu Pharmaceutical Co., Ltd. and Zhuhai Hengqin Deyunjia International Trade Co., Ltd., with a registered capital of 20 million yuan, of which Jianfeng Pharmaceutical contributed 11 million yuan in cash, accounting for 55% of the registered capital. Gefu Pharmaceuticals invested 5 million yuan in the evaluation of two proprietary technologies of "diazepam suppository" and "acetaminophen suppository, 25% of the registered capital; De Yunjia contributed 4 million yuan in cash, accounting for 20% of the registered capital. The company's registered address is in Jinxi Development Zone, Jinhua City. It will rent the existing factory building of Jianfeng Pharmaceutical Jinxi Pharmaceutical Factory for renovation, and strive to absorb their respective expertise and adopt appropriate advanced technology and scientific management methods. A modern pharmaceutical enterprise focusing on the research and development, production and sales of pharmaceutical preparations for infants and children. In this cooperation, the corresponding products of "diazepam suppository" and "acetaminophen suppository", which Ge Fu pharmaceutical has invested in with proprietary technology evaluation, have been listed in Germany, among which diazepam suppository is a therapeutic drug for anti-anxiety, sleep disorder and muscle tension increase; acetaminophen is used for fever caused by cold or cold, and also for relieving mild to moderate pain. After the establishment of the joint venture company, it will be based on these two know-how.
2020
07-31
Jinhua City People's Congress Leaders Peak Survey
On July 26, Cai Jian, deputy director of the Jinhua Municipal People's Congress, Chen Zhishi, secretary general of the Standing Committee of the National People's Congress, and a group of four people visited Jianfeng to conduct research on the introduction of talents and technological innovation, and to communicate with Jiang Xiaomeng, Yu Jianhong, Huang Jinlong, Xiang Chongping, Lan Xiaolong and other group company leaders conducted in-depth exchanges. (this newspaper reporter)
2020
07-31