Announcement on the Subsidiary's Receipt of the Decision of the Environmental Protection Department Ordering to Stop Production and Remediation
Release time:
2020-08-05
Securities Code: 600668 Securities Abbreviation: Jianfeng Group Announcement No.: 2018-020
Bond Abbreviation: 13 Jianfeng 02 Bond Code: 122344
Zhejiang Jianfeng Group Co., Ltd.
Announcement
of the Company's Board of Directors and all directors guarantee that there are no false records, misleading statements or major omissions in the contents of this announcement, and shall bear individual and joint liabilities for the authenticity, accuracy and completeness of its contents
Recently, Anhui Xinbeika Chemical Co., Ltd. (hereinafter referred to as "Anhui Beika"), a subsidiary of the company, received the Dongzhi County Environmental Protection Bureau's "Decision on Ordering Suspension of Production and Rectification" (
Donghuan Zit [2018] No. 04), the main contents are hereby announced as follows:1. the contents of the "Decision on Ordering to Stop Production and Rectification"
(I) Investigation and Findings of Environmental Violations
After investigation by our bureau, it is found that your company has implemented the following environmental violations: "Your company's annual output of 500
tons of acetamiprid is in production, and the valve of the gas outlet pipeline of the activated carbon adsorption tank of the waste gas treatment facility in the 201 workshop is closed, the waste gas in the tank overflows from the outlet of the sewage pipe and the inlet and outlet of activated carbon replacement, etc., and the smell on site is heavy." The above facts ofare based on evidence such as the on-site (survey) record, investigation and inquiry record, on-site photos and so on on June 22, 2018
by our bureau.The above actions of your company violate the provisions of Article 20, paragraph 2, of the the People's Republic of China Air Pollution Prevention and Control Law.
The basis and type of the (II)'s decision to suspend production for rectification
According to Item (III) of Paragraph 1 of Article 99 of the the People's Republic of China Air Pollution Prevention and Control Law, and Item (I) of Article 6 of the Measures for the Implementation of Restrictions on Production and Suspension of Production by Environmental Protection Authorities, our bureau has decided to order your company to implement suspension of production for rectification.
Implementation method and deadline for (III) shutdown rectification
1
, your company shall immediately stop production from the date of receipt of this decision, and take corrective measures to formulate and implement the rectification plan.2
. Your company shall report the rectification plan to our bureau for the record and make it public within 15 working days after receiving this decision. The rectification plan shall determine the corrective measures, the progress of the project, the guarantee of funds and the responsible personnel.3
. After your company completes the rectification task, it shall report the completion of the rectification task and the public disclosure of the rectification information to our bureau for the record within 15 working days.4
. Your company shall not have any illegal pollutant discharge during the rectification period, and shall not resume production without reporting the completion of the rectification task to our bureau for the record.The period of suspension of production for rectification is from the date of service of this decision to the date of cancellation of the suspension of production for rectification.
Our bureau will supervise your unit after the implementation of the shutdown rectification, and conduct follow-up inspection after the shutdown rectification is lifted. If your company refuses to carry out rectification as required or commits illegal acts after resuming production, our bureau will impose administrative penalties or administrative treatment in accordance with the law according to your company's illegal circumstances and environmental consequences.
Ways and Time Limit for (IV) to Apply for Administrative Reconsideration or File Administrative Litigation
If your company does not accept this decision, it may apply for administrative reconsideration to Chizhou Municipal Environmental Protection Bureau or Dongzhi County People's Government within 60 days from the date of receipt of this decision in accordance with the provisions of Article 9 of the the People's Republic of China Administrative Reconsideration Law, an administrative lawsuit may also be brought to the people's Court of Dongzhi County within six months from the date of receipt of this decision in accordance with Article 46 of the the People's Republic of China Administrative procedure Law. If an application for administrative reconsideration or an administrative lawsuit is filed, the implementation of this decision shall not be suspended.
If you do not apply for administrative reconsideration, file an administrative lawsuit, or perform this decision within the time limit, our bureau will apply to the people's court for enforcement in accordance with the law.
2. Rectification Measures
Company attached great importance to the above decision and immediately requested Anhui Beika to actively cooperate with the environmental protection department in inspection and stop illegal acts. The specific measures are as follows:
1
. In response to the incident, the company instructed Jianfeng Pharmaceutical to immediately set up an environmental protection incident emergency working group to investigate the incident and supervise the rectification; at the same time, arrange the company's production enterprises to conduct a comprehensive environmental self-examination to prevent the occurrence of similar incidents.2
, prepare a rectification plan and arrange special funds to further upgrade the existing waste gas treatment system in Beika, Anhui Province.
3. During the period of shutdown and rectification, Anhui North Carolina will be arranged to carry out annual routine equipment maintenance to ensure the normal operation of production facilities after resumption of production.
Anhui North Carolina will complete the rectification as soon as possible and report the completion of the rectification to the Environmental Protection Bureau, so as to resume normal production as soon as possible.Impact of 3. on the Company
2018
In January and August, the board of directors of the company approved that the subsidiary Zhejiang Jianfeng Pharmaceutical Co., Ltd. acquired 55% of the equity of Shanghai Beika Pharmaceutical Technology Co., Ltd. by acquiring shares and increasing capital. Anhui Beika is a wholly-owned subsidiary of Shanghai Beika Pharmaceutical Technology Co., Ltd. In May 2018, the industrial and commercial change registration and handover procedures for the investment were completed. In accordance with the "Application Guide to Enterprise Accounting Standards No. 20-Business Combinations", the Company has included Shanghai Beika Pharmaceutical Technology Co., Ltd. and its subsidiaries in the scope of the Company's consolidation since June 2018.At the end of 2017
, the company's total assets were 41.76 .1 billion yuan, and the net assets attributable to the owners of the parent company were 2.627 billion yuan. In 2017, the company realized operating income of 2.827 billion yuan and realized net profit attributable to the owners of the parent company. 0.348 billion yuan. At the end of 2017, Anhui North Card's total assets were 0.047 billion yuan and net assets were 0.012 billion yuan. Anhui North Card's annual operating income in 2017 was 0.046 billion yuan and net profit was -0.008 billion yuan. Anhui North Card's total assets were about 1.13 of the company's total assets and its operating income was about 1.63 of the company's operating income. Anhui North Card has a small impact on the Company's overall operating income and efficiency.
The company will strictly follow the "Shanghai Stock Exchange Stock Listing Rules" and other relevant requirements to do a good job of information disclosure in a timely manner. Please invest rationally and pay attention to investment risks.This is to announce
Zhejiang Jianfeng Group Co., Ltd. Board of Directors
July 5, 2018
More information
The Sixth Plenary Session of the 18th Central Committee of the Communist Party of China was held in Beijing from October 24 to 27. It reviewed and approved the "Several Guidelines on Political Life within the Party under the New Situation" and the "Regulations on Inner-Party Supervision of the Communist Party of China. On November 22, the party committee of the group company successively held party committee and branch secretary meetings to learn the spirit of the sixth Plenary session of the 18th CPC Central Committee and put forward requirements for organizational construction and party member management. At the branch secretary meeting, Jiang Xiaomeng, secretary of the party committee of the group company, preached the main contents of "some guidelines on Inner-Party political Life under the New situation" and "regulations on Inner-Party Supervision of the Communist Party of China. He pointed out that seeking truth from facts, integrating theory with practice, keeping close ties with the masses, criticizing and self-criticism, democratic centralism, and strict party discipline are the basic norms and working principles of inner-party political life accumulated by the Communist Party of China for several generations. In the new social environment, some party members and cadres have bred some unhealthy atmosphere, which has damaged the image and interests of the party, the Sixth Plenary Session of the 18th Central Committee of the Communist Party of China proposed to strengthen and standardize the political life within the party, take the party constitution as the foundation, adhere to the party's political line, ideological line, organizational line and mass line, strive to enhance the political, contemporary, principled and fighting nature of the party's political life, and strive to enhance the party's ability of self purification, self improvement, self innovation and self improvement, Efforts should be made to improve the party's leadership and governance level, efforts should be made to safeguard the authority of the Party Central Committee, ensure the unity and unity of the party, maintain the advanced nature and purity of the party, and strive to form a centralized, democratic and disciplined party in the whole party
2020
07-31
Jinxi plant environmental protection facilities through the completion of acceptance
On November 1, Jianfeng Pharmaceutical Jinxi Pharmaceutical Factory successfully obtained the approval from Zhejiang Environmental Protection Department that the environmental protection facilities of the project passed the completion acceptance, and a key work of Jianfeng Pharmaceutical in 2016 came to an end. Jianfeng Pharmaceutical's annual output of 35 tons of cephalosporins, anti-tumor drugs and other raw material production lines and various preparation production lines technological transformation projects started construction in Jinxi Development Zone in October 2012 and were almost completed in September 2015. The construction of the project strictly abided by the "three simultaneous" system of environmental protection, conscientiously implemented the requirements in the environmental impact assessment report and its approval documents, and invested 19.34 million yuan in environmental protection facilities. The plant has basically realized the separation of clean and sewage. A new wastewater treatment system with a daily treatment capacity of 700 cubic meters and a "physical, chemical and biochemical" treatment process has been built, and an online monitoring device networked with the environmental protection department has been installed. All kinds of production wastewater, public works wastewater and domestic sewage are treated by the wastewater station and sent to Jinxi Sewage Treatment Plant for centralized treatment; there is an RTO regenerative incineration device of 10000 cubic meters per hour and a centralized treatment device of 4000 cubic meters per hour for chlorine-containing organic waste gas. All kinds of waste gas are discharged after collection and treatment. In October 2015, with the approval of Jinhua Economic and Technological Development Zone Branch of Jinhua Environmental Protection Bureau, the trial production of Jinxi project was carried out. After more than half a year of operation, in early July 2016, Zhejiang Environmental Monitoring Center Station carried out completion acceptance monitoring of environmental protection treatment facilities such as waste water and waste gas of Jinxi Pharmaceutical Factory, and issued a completion acceptance monitoring report of environmental protection facilities at the end of August.
2020
07-31
Jinxi plant environmental protection facilities through the completion of acceptance
On November 1, Jianfeng Pharmaceutical Jinxi Pharmaceutical Factory successfully obtained the approval from Zhejiang Environmental Protection Department that the environmental protection facilities of the project passed the completion acceptance, and a key work of Jianfeng Pharmaceutical in 2016 came to an end. Jianfeng Pharmaceutical's annual output of 35 tons of cephalosporins, anti-tumor drugs and other raw material production lines and various preparation production lines technological transformation projects started construction in Jinxi Development Zone in October 2012 and were almost completed in September 2015. The construction of the project strictly abided by the "three simultaneous" system of environmental protection, conscientiously implemented the requirements in the environmental impact assessment report and its approval documents, and invested 19.34 million yuan in environmental protection facilities. The plant has basically realized the separation of clean and sewage. A new wastewater treatment system with a daily treatment capacity of 700 cubic meters and a "physical, chemical and biochemical" treatment process has been built, and an online monitoring device networked with the environmental protection department has been installed. All kinds of production wastewater, public works wastewater and domestic sewage are treated by the wastewater station and sent to Jinxi Sewage Treatment Plant for centralized treatment; there is an RTO regenerative incineration device of 10000 cubic meters per hour and a centralized treatment device of 4000 cubic meters per hour for chlorine-containing organic waste gas. All kinds of waste gas are discharged after collection and treatment. In October 2015, with the approval of Jinhua Economic and Technological Development Zone Branch of Jinhua Environmental Protection Bureau, the trial production of Jinxi project was carried out. After more than half a year of operation, in early July 2016, Zhejiang Environmental Monitoring Center Station carried out completion acceptance monitoring of environmental protection treatment facilities such as waste water and waste gas of Jinxi Pharmaceutical Factory, and issued a completion acceptance monitoring report of environmental protection facilities at the end of August.
2020
07-31
Jinxi plant environmental protection facilities through the completion of acceptance
On November 1, Jianfeng Pharmaceutical Jinxi Pharmaceutical Factory successfully obtained the approval from Zhejiang Environmental Protection Department that the environmental protection facilities of the project passed the completion acceptance, and a key work of Jianfeng Pharmaceutical in 2016 came to an end. Jianfeng Pharmaceutical's annual output of 35 tons of cephalosporins, anti-tumor drugs and other raw material production lines and various preparation production lines technological transformation projects started construction in Jinxi Development Zone in October 2012 and were almost completed in September 2015. The construction of the project strictly abided by the "three simultaneous" system of environmental protection, conscientiously implemented the requirements in the environmental impact assessment report and its approval documents, and invested 19.34 million yuan in environmental protection facilities. The plant has basically realized the separation of clean and sewage. A new wastewater treatment system with a daily treatment capacity of 700 cubic meters and a "physical, chemical and biochemical" treatment process has been built, and an online monitoring device networked with the environmental protection department has been installed. All kinds of production wastewater, public works wastewater and domestic sewage are treated by the wastewater station and sent to Jinxi Sewage Treatment Plant for centralized treatment; there is an RTO regenerative incineration device of 10000 cubic meters per hour and a centralized treatment device of 4000 cubic meters per hour for chlorine-containing organic waste gas. All kinds of waste gas are discharged after collection and treatment. In October 2015, with the approval of Jinhua Economic and Technological Development Zone Branch of Jinhua Environmental Protection Bureau, the trial production of Jinxi project was carried out. After more than half a year of operation, in early July 2016, Zhejiang Environmental Monitoring Center Station carried out completion acceptance monitoring of environmental protection treatment facilities such as waste water and waste gas of Jinxi Pharmaceutical Factory, and issued a completion acceptance monitoring report of environmental protection facilities at the end of August.
2020
07-30
Daye Jianfeng Safety Standard was awarded as the only award-winning enterprise in daye city in 2015.
Due to the achievements made in the establishment of secondary safety production standardization, daye peak cement company recently received a special award of 200000 yuan from daye municipal government. In order to encourage industrial and commercial enterprises in the region to improve their production safety, daye municipal government set up a special fund in 2015, stipulating that 200000 yuan will be awarded to those who pass the secondary safety standardization review before December 31, 2015. It is understood that among the industrial and commercial enterprises in daye city, there were 4 enterprises that applied for and passed the examination in 2015, but only daye peak passed the examination before December. Therefore, Daye Peak has become the only enterprise that has won the special award for the establishment of the safety standard in Daye City in 2015. (Ye Meifang)
2020
07-31
Two Cement Enterprises Start to Implement "Big Patrol Inspection"
With the change of the competition situation in the industry, the profit space of cement production enterprises has been greatly squeezed. Reducing costs and increasing efficiency and job optimization have become the inevitable choice to improve the enterprise's own development ability and enhance the core competitiveness. In accordance with the requirements of the group company to realize the transformation from extensive management to lean management, combined with the advanced experience of peer enterprises, recently, Yunnan peak, daye peak two enterprises have implemented "big inspection" to promote the overall optimization of posts. On November 1, daye peak post inspection officially started full operation, starting from the limestone storage yard at the source of the production line to the cement storage. the original 15 posts were merged, and the best experienced mechanics, electricians and post workers were transferred to form a large inspection class, which was mainly responsible for on-site emergency disposal and post routine maintenance to ensure the normal production of the whole production line. In order to ensure the smooth implementation of the large-scale inspection, daye peak management team has repeatedly communicated and discussed with the heads of relevant workshops and departments, and held a special workshop post optimization promotion meeting in September to clarify objectives and responsibilities, formulate implementation steps, and do a lot of preparatory work. At the kick-off meeting for the implementation of the large-scale inspection on October 31, Zhang Fengliang asked daye peak employees to recognize the current situation of serious cement overcapacity and cruel market competition, understand the necessity of implementing the large-scale inspection, and asked the workshop leaders to do a good job in training and guiding the employees, shorten the transition period, normalize the operation of the large-scale inspection as soon as possible, and at the same time, managers should also change their working ideas and concepts and do a good job in full-time, strengthen the inspection, overhaul and maintenance of the regular day shift, and find and solve the problems existing in the equipment and process in time.
2020
07-30